Free Essay

Nasa Leadership Program

In:

Submitted By ttqq
Words 3759
Pages 16
National Aeronautics and Space Administration

Academy of Program / Project & Engineering Leadership Space-to-Space Communications System (SSCS)

www.nasa.gov

casestudy

SPACE TO SPACE COMMUNICATIONS: IN-HOUSE HARDWARE DEVELOPMENT

When Johnson Space Center’s Matt Lemke showed up for work as the project manager of the Space-to-Space Communications System at the tail end of 1994, he discovered that the project he had inherited was not the one he expected. On his second day on the job, Lemke, an experienced avionic engineer but newly assigned project manager, attended a kickoff meeting with Litton Industries, who had recently been selected as the project’s prime contractor. Lemke had read the contract beforehand and understood the terms of the agreement. He planned to hand the Litton team a set of engineering drawings that had been developed before his arrival so they could get started. After handshakes and introductions, he turned to his NASA colleague who had supported the contract agreement with Litton just weeks before, and asked her for the drawings. Her response stunned Lemke: “What drawings?” A First-of-Its-Kind Radio System The Space-to-Space Communications System (SSCS) is a sophisticated two-way data communication system designed to provide voice and telemetry among three on-orbit systems: the Space Shuttle orbiter, the International Space Station (ISS), and the Extra Vehicular Activity Mobility Unit (EMU). (An EMU is a space suit worn by an astronaut during a space walk, or Extravehicular Activity.) SSCS is designed to allow simultaneous communication among up to five users. The system comprises three product lines: space suit radios (SSER), the Shuttle orbiter radio (SSOR), and the Space Station radio (SSSR). All three share some commonalities, but have unique features and different designs. (See Appendices 1.1 and 1.2.) This networked communications system was conceived as a “breadboard” (engineering prototype) concept in the avionic systems laboratories at Johnson Space Center (JSC) in the early 1990s with funding from the Space Station program. A few years later, the Shuttle program authorized SSCS into formal development to satisfy a critical need for interoperable space communications among the three vehicles in order to execute the construction of the ISS. Lockheed Martin, which provided technical support service to the JSC Engineering Directorate, did much of the early design work on the prototype system. (See Appendix 1.3.) An In-House Development After soliciting proposals from commercial contractors including Rockwell and Motorola, NASA decided to treat SSCS as an “in-house” development, meaning that its own personnel would design and deliver the system. (See Appendix 1.4.) The rationale behind this decision was twofold. JSC Engineering liked to provide its technical workforce with opportunities to gain hands-on experience working with hardware. This ensures that the Agency retains a highly skilled workforce that knows the challenges of developing new technologies across a project life cycle and can engage with contractors on a peer-to-peer level. The primary reason for this decision, however, was cost. 1

Motorola and Rockwell had independently proposed to build the system for over $90 million. The NASA team thought it could handle the job to design the system and to outsource the manufacturing for $20 million, a substantial savings for the government. NASA held a competitive bidding process to hire a manufacturer for the radios, and it selected Litton Industries from the three proposals it received to serve as prime contractor. Litton was expected to refine the manufacturability of the design during the Preliminary Design Review (PDR) and Critical Design Review (CDR) and subsequently manufacture the flight articles, with anticipated efficiencies of scale during the production phase. The contract called for Litton to work on a cost-plus basis during the design refinement phase and then on a firm-fixed price basis for the actual manufacturing of the radios. NASA retained primary design responsibility for the SSCS, while Litton served as the manufacturing vendor. (See Appendix 1.3.) A Difficult Reorganization The formal start of the SSCS project coincided closely with a reorganization within the Engineering Directorate at JSC. Two divisions, the Tracking and Communications Division and the Flight Data Systems Division, merged into a new Avionic Systems Division. At the same time, a new Project Management Office was created to manage the engineering project teams that in the past had interacted directly with their “customers” (e.g., the Space Shuttle or Space Station programs). Both administrative changes led to mixed morale, and several key engineers with radio expertise opted not to work for the Project Management Office, which now had oversight over the SSCS project. At about the same time, the Engineering Directorate awarded a new engineering support contract to Lockheed. While Lockheed was also the previous support contractor, the new contract had a number of provisions that drove off many engineers. All of the contractor designers on SSCS left the project in the six months prior to Litton being awarded the manufacturing contract. Starting Over In short, Lemke found himself at the beginning of his first significant NASA project management assignment under a new internal organization, with no engineering drawings, none of the designers who had worked on the earlier phase of the development, and a project team with no expertise in the SSCS complex radio system architecture. At this point he could apprise management of the gravity of the situation or he could find a path forward. He chose to persevere. He had a team that was ready to work hard, despite its inexperience with the inherited technical design. The project itself was a motivator; it was the biggest project in the division, the work was important and challenging, and it offered a rare opportunity to do hands-on hardware development. In Lemke’s estimation, hard work could overcome the setback he had been handed. Lemke and his in-house team of designers began the painstaking process of deriving drawings from the prototypes, using calipers, Ohm meters, and every other reverseengineering tool of the trade to determine the exact specifications of the boards. Every

2

measurement was an opportunity for a mistake; a single missed connection might mean that an entire circuit wouldn’t work. The NASA team’s progress proved excruciatingly slow, and Lemke realized that at this pace the project would never be completed. He approached Litton, the prime contractor, and explained the situation. Litton said that its engineers could re-create the drawings. Lemke initiated a contract change and handed the boards over to Litton. Litton was eager to prove itself on this project; the SSCS contract was its first at JSC. It hoped to expand its business there, and was willing to go to great lengths to ensure that the SSCS project was successful. At the end of eight months, the drawings were complete. Lemke’s project was now where it should have been when he arrived for his first day on the job. A Schedule Driven by Space Station The primary consideration driving the SSCS schedule was the construction of the Space Station. Since the Space Shuttle was an existing operational program with working radios, there was not schedule pressure from the Shuttle program or the EVA Project Office to deliver the SSCS by a certain flight. The Shuttle program maintained a busy launch schedule in the late 1990s, and another flight was always just around the corner. The Space Station, however, had hard and fast deadlines. From Lemke’s vantage point, the schedule pressure associated with Space Station stemmed from political considerations, not technical concerns. Most of the Space Station was being built by a large government contractor that was running behind schedule and over budget. As a result, any piece of government-furnished equipment (GFE) that was late, regardless of its function, provided an opportunity for the contractor to claim that the government was holding up the works and impeding its ability to deliver on time. “There was enormous pressure to deliver on schedule, even though everybody knew Station was way behind, even though everybody knew you didn’t need those radios to test out the U.S. lab module,” Lemke said. “It was an add-on. It was a game of chicken, and the government couldn't be late delivering.” An Immature Design The project sailed through its multi-staged Preliminary Design Reviews (PDR) and Critical Design Reviews (CDR), but the time it had lost re-creating the drawings also inhibited the maturation of the design. (See Appendix 1.5.) Litton was supposed to have spent that time turning the engineering prototypes into radios that could be manufactured and building some test units. Instead, Litton re-created the laboratory units, which didn’t meet the project’s requirements. This was clear from the performance of the SSCS Design Verification Test Units (DVTU) based on the drawings Litton had faithfully recreated. The DVTUs could communicate over the radio waves, but didn’t work well as a five-radio network.

3

With the schedule to deliver the radio for the Space Station closing in, Lemke elected to make the necessary fixes to the DVTUs in a piecemeal fashion rather than inserting another DVTU cycle to improve the design and address the problems on a systems level. As long as his team practiced good configuration control, the working DVTUs would lead straight to the qualification test unit and then the first flight production unit. Division management agreed with this plan in the hopes of meeting the Station delivery schedule. By this stage, Litton informed Lemke that it was having problems with its units. None of the units would consistently pass the specification tests. There was now a real concern that many key parts had a combination of quality and tolerance problems. However, the greatest concern was the growing realization that the overall NASA design had problems. “They were saying, hey, we don’t think your design really has enough margin. It doesn’t really seem to us that these are very manufacturable, that we’re going to be able to get repeatable results,” Lemke said. The chief engineer on Lemke's team was confident in its design, however, and thought that Litton might be looking for an expensive extension of the cost-plus part of its contract. The chief engineer asserted that the problem was with Litton’s manufacturing processes, not the design. Lemke pressed Litton to stick to the design and build the qualification test units as though they were flight units. Litton did as its customer requested. At this point the commonalities among the different radios became extremely critical. The modem and receiver boards, for example, were identical for all of the radios, so flaws in one would be reproduced in the others. Once Litton built a qualification unit for each of the three radios, the problems it had predicted began to surface. The units did not yield repeatable results, and the RF (radio frequency) performance was below par. A seemingly endless series of quick fixes ensued at the same time that Litton kept producing more radios, which led to constant reworking of all the existing radios, with changes that had to be tracked by serial numbers and recorded in data packages. The project operated in “fire drill mode,” scrambling from one problem to the next, which led to schedule changes on a weekly basis and no time for rigorous systems testing. During this time Lemke temporarily left his position as the SSCS project manager for another job. His replacement, Dave Lee, had joined the team earlier as Lemke's deputy and was fully aware of the difficulties Lemke had faced along the way. The managerial transition was a smooth one, but no one could have predicted the need for Lemke's return to once again help lead the project out of trouble. Within a year Lemke was back, and the team continued to persevere.

Flight Time The radios made it through acceptance testing, performance testing, and qualification testing. Some individual radios did not perform as well as expected, but they passed.

4

The time came to modify the Space Shuttle Orbiter and the space suits to accommodate the new radios. In the fall of 1998 the SSCS underwent a test flight on Space Shuttle Mission STS-95, which did not include an EVA (space walk). The test flight uncovered some minor glitches, including an instance in which one radio would not talk to another. This problem was attributed to operator error and solved by re-cycling the system’s power (turning it off and back on). The SSCS team thought the radios were ready for a real in-flight trial. The project delivered its radio to the Space Station in November 1998. At this point, the problems seemed to be getting smaller; there were still lots of fixes, but the work seemed manageable. Around the same time, Lemke and Lee accompanied the head of the Avionic System Division and other senior NASA managers to Litton to re-negotiate the requirements for the radios. The purpose was twofold: to establish a realistic baseline for technical performance on measurements such as RF output and sensitivity, and to clarify expectations for all the stakeholders—the project team, Litton, and the three customers for the radios. With the new baseline, the project had a clean slate. Preparations began at Kennedy Space Center (KSC) for Mission STS-96, which would launch in the spring of 1999. In the course of testing on the launch pad, the space suit radio (SSER) began making inexplicable noises. Lee and Lemke, who at this point was on board as a consultant to the project, flew to KSC to troubleshoot the situation. They began working around the clock trying to reproduce the intermittent noises that the radios were now making, but the causes eluded them. As they heard new sounds they characterized them with descriptive nicknames: motor-boating, rain on the roof, laryngitis. Their testing led to an examination of the radio environment at KSC, which was filled with RF interference. KSC conducted studies of the frequencies that filled the airwaves and tried to provide a quiet RF environment for testing the SSCS. It didn’t help; the team could never correlate the noises with any specific RF interference. But after hundreds of hours of testing, it managed to collect enough signatures—specific noises that behaved the same way each time—that it was able to develop recovery procedures, including power-cycling, that would allow the radio operators to work around the noises. With the launch fast approaching, the Shuttle crew had to be trained in recovery procedures in case the radios malfunctioned in flight. A Mission Operations Directorate official taught the crew how to respond, and made a cue card that actually flew on the Shuttle. (The crew was already trained in the use of hand signals in the event of a complete radio failure.) The last-minute training proved necessary. Astronauts experienced “motor-boating” during an EVA, and the procedures allowed them to recover gracefully from the malfunction. The Shuttle crew successfully carried out its mission despite the problems with the radios. * * * *

5

Aftermath and Recovery The problems with the SSCS before and during STS-96 were, in Dave Lee’s words, “a huge black eye for the project and the JSC Engineering Directorate” within NASA. The debriefings of the STS-96 crew after the flight drew the attention of senior management. The SSCS had failed dramatically in a high-risk and high-visibility situation. The Shuttle and the EMUs had to be retrofitted with the original radios at once for the next flight. At the same time, the failure also marked the beginning of the project’s turnaround. The SSCS team got unmistakable orders from management: go fix the system. Cost and schedule were secondary to finding the root causes of the problems. Every element of the design was reviewed. The break in the action allowed the team to conduct the extensive systems testing that it had foregone in the run-up to its first flight. The project also received additional resources to bring in experts who could help solve the problems. One expert likened the process to peeling an onion; each layer revealed its own problem, and peeling more deeply led to others. On close examination, it turned out there were multiple root causes for the failures. The receiver design was hyper-sensitive to RF interference. Taxicabs in Argentina were transmitting on a frequency that was close enough to cause noises. The signal processor software was also flawed. It required precise data from the modem—and the modem was fed by the receiver—or it had software problems, and would get confused and malfunction. The algorithms for networking the radios required extensive reworking. In addition, the testing revealed several problems unrelated to the root causes, such as poorly written software routines and floating leads in the hardware design. A year after STS-96, the SCSS was re-deployed for STS-101 in May 2000. There was a problem with the reference level on this flight, but the phantom noises that had plagued the system previously were gone. By the time of STS-106 four months later, the SSCS achieved error-free operations for the first time. It has continued to do so ever since. In the end, Lemke saw the failure as turning point that led to the resolution of the project’s difficulties. “That’s where we got to spend the time with our design to really get to the root cause. We got to do the testing, got to find out where the flaws were, and fix it,” he said. “It was just getting the team, the time, and the management support to solve it. There were no more Band-Aids. ‘Go solve it, and whatever it takes, you do it.’”

6

Appendix 1: Supporting Materials 1.1. General Project Description The Space to Space Communications System (SSCS) allows vehicles in close proximity to communicate voice, commands and telemetry via a radio frequency (RF) link. Each space vehicle utilizing the SSCS provides control, data, voice and power cabling as applicable. These cables are not considered part of SSCS.

Figure 1.1: Three radios enable communication among the Space Shuttle Orbiter (SSOR), the International Space Station (SSSR), and astronauts engaged in extravehicular activities (SSER). (Source: NASA SSCS Critical Design Review presentation, April 29, 1996.)

7

1.2. Space to Space Communications System Radios a. Space to Space EMU Radio (SSER)

Figure 1.2a: The Space to Space EMU Radio (SSER) allows astronauts to communicate with the Shuttle Orbiter and/or International Space Station during EVAs. (Source: David Lee, NASA)

8

b.

Space to Space Orbiter Radio (SSOR)

Figure 1.2b: The Space to Space Orbiter Radio (SSOR) allows the crew aboard the Shuttle Orbiter to communicate with the International Space Station and/or astronauts conducting EVAs. (Source: David Lee, NASA)

9

c.
• • • • •

Space to Space Station Radio (SSSR)

• • • •

Space to Space Communications System (SSCS) Time Division Multiple Access (TDMA) radio Mounted in Avionics Rack #1 in the U.S. Laboratory Module of the ISS Provides voice communications between the ISS and EVA astronauts. Receives suit status and biomedical signals from the EMU Provides a voice and telemetry/command link with the Orbiter Completely controlled by the Command and Control Multiplexer/Demiltiplexer (C&CMDM) on the ISS • Provides decryption of command link from the Orbiter to the ISS at one 64 word command/second • Provides a telemetry link from the ISS to the Orbiter • Command and control of the SSSR ISS provided mechanical interface - ‘6B’ box design Designed at JSC by a team of engineers from the Avionic Systems Division and Lockheed-Martin Manufactured by Litton Amecom Space Systems Operations First flight scheduled for May 1999 on STS 98 (ISS assembly flight 5A)

Boeing Picture

MODEM A

TRANSMITTER A DUPLEXER A RECEIVER A

CAVITY FILTER A

DIRECTIONAL COUPLER CP1

DIRECTIONAL COUPLER CP3

POWER DIV PW3

TO/FROM EXT ANT

AUDIO/CLK IN AUDIO OUT

SIGNAL PROCESSOR A

MODEM/SIGNAL PROCESSOR PWR CONVERTER A

• • • •

CMDS/DATA CHA CMDS/DATA CHB 120 VDC

1553 INTERFACE BOARD A

120/28 DC/DC MASTER A EMI FILTER A 120/28 DC/DC MASTER A

POWER DISTRIBUTION BOARD A IAA SW

TO/FROM IAA POWER DIV PW1 POWER DIV PW2

120 VDC RTN 120 VDC 120 VDC RTN CMDS/DATA CHA CMDS/DATA CHB 1553 INTERFACE BOARD B EMI FILTER B 120/28 DC/DC MASTER B 120/28 DC/DC MASTER B POWER DISTRIBUTION BOARD B

TO/FROM AIRLOCK TERM

AUDIO/CLK IN AUDIO OUT

SIGNAL PROCESSOR B TRANSMITTER B DUPLEXER B MODEM B RECEIVER B

MODEM/SIGNAL PROCESSOR PWR CONVERTER B

• • • • • • • •

CAVITY FILTER B

DIRECTIONAL COUPLER CP2

DIRECTIONAL COUPLER CP4

POWER DIV PW4

TO/FROM EXT ANT

Two radios within one enclosure Fully redundant except for a single RF switch on the Internal Antenna Assembly (IAA) Each radio can operate at either 414.2 MHz or 417.1 MHz Two power modes • Low power: 0.25 Watts (+24dBm) resulting in an operational range of 80 meters • High power: 5.0 Watts (+37 dBm) resulting in an operational range of up to 7 km along the Orbiter/ISS rendevous trajectory 6 antenna ports: 4 External Antennas, IAA, and Airlock Antenna Operational from 20 °F to 120 °F while sitting on a cold plate Frequency shift keying modulation with a burst rate of 695 kbps Intermediate frequency of 21.4 MHz Bit Error Rate performance of 1x10-5 when the RF input is -86.5 dBm Maximum operational power draw from the ISS of 72 Watts in high power mode Actual dimensions of 13.25”x18.6”x9.15” Weight is under 40 pounds

Figure 1.2c: The Space to Space Station Radio (SSSR) allows the crew aboard the International Space Station to communicate with the Shuttle Orbiter and/or astronauts conducting EVAs. (Source: David Lee, NASA)

10

1.3. SSCS Roles and Responsibilities (Notional)

Figure 1.3: Roles and responsibilities for the various elements of the SCSS program. (Source: David Lee, NASA)

11

1.4. SSCS Government Furnished Equipment (GFE) Deliverables

Figure 1.4: Many Space to Space Communications System components were delivered as Government Furnished Equipment (GFE) by the Avionic Systems Division of the Johnson Space Center’s Engineering Directorate. (Source: NASA SSCS Critical Design Review presentation, April 29, 1996)

12

1.5. Project Timeline

Figure 1.5: Project timeline and milestones from initial concept through 2005. Note: error-free operations continued up to the time of publication of this case study in early 2007. (Source: David Lee, NASA)

13

Similar Documents

Premium Essay

Space Program Downfall

...hole that was punctured into the leading edge of the aircraft during takeoff (NASA). This hole resulted in an excess heating on the leading edge of the wing and then the failure of the wing. This was just the physical cause of the accident that destroyed the shuttle. There were other aspects of the entire NASA program that could have prevented this from occurring but there were failures in the system. Not one factor contributed Columbia accident, but a combination of factors are the root of the cause. The purpose of this case is to input the Columbia Accident Investigation Board (CAIB) in the Burke-Litwin model. This is not to reorganize the very through report by CAIB, but to see where the findings can fit in to show how both internal and external factors that affect change within NASA. One of the most important factors to understand with the Burke-Litwin model is that all 12 factors interact and affect each other. NASA just like any other organization can have negative traits that affect positive traits. This relationship is well demonstrated using the Burke-Litwin model. Body The first section of the Burke-Litwin model is based on the transformational variables within an organization. Within an organization these variables are the vision to an organization or its overall goal and sense of purpose. Drastic changes with these variables can cause wanted or unwanted change within an organization. NASAs...

Words: 1746 - Pages: 7

Premium Essay

Acquisition Planning

...the National Aeronautics and Space Administration (NASA), have carried out acquisition planning. HHS, DHS and NASA are required to have written acquisition plans which must be close to what the elements in the FAR states. DHS and NASA also have the cost estimates and requirements documents when preparing the acquisition plan along with the consideration if lessons learned. HHS, DHS and NASA have different dollar thresholds when written acquisition plans are required. HHS written acquisition plan threshold was $500,000 and above as DHS was $10,000 and above and NASA was $10 million and above the written acquisition plan. A written acquisition plan helps to ensure thorough planning, which DHS and NASA prepared the written plan even though they were not required to. NASA and HHS require different written acquisition plans for contracts. NASA contracts valued at $10 million and above is necessary for a written acquisition plan because it improves documentation and helps with the training of staff that does not have that much experience. HHS contract valued at $500,000 and above requires a written acquisition plan because it gives the procurement office a better look at the overall acquisition planning. Compare and contrast how these same three (3) agencies have established policies that set different requirements and levels of oversight for acquisition planning. When preparing acquisition planning DHS and NASA would incorporate lessons Acquisition Planning...

Words: 1034 - Pages: 5

Premium Essay

Policy Analysis of Nasa's Budget

...Policy Analysis of the Budget Percentage Appropriated to NASA February 5, 2013 Introduction to the Policy Issue. As it stands today, the National Aeronautics and Space Administration is at a crossroads. It seems a lack of direction has plagued the organization in recent years and with the close of the Space Shuttle program this past year, the questions looming have become even more exposed. What next? Recent budget cuts have left NASA funded at its lowest level in four years5, forcing the space agency to juggle priorities (see Figure 4) and think uncharacteristically “inside the box” for answers to this question. Background on the Issue. NASA's budget peaked in the period 1964-1966(see Figure 2), during the height of construction efforts leading up to the first moon landing under the Apollo program. Since then, NASA has undertaken many projects, while its portion of the national budget has been slowly chipped away. There are many ideas, but no definite decisions on what NASA should set to achieve next. Without proper leadership, direction, and funds, NASA and the United States will soon take a back seat in the ‘space race’. Effects of Present Problem and Current Policies. Identifying policy alternatives is important because NASA’s impact can be seen through: * Being a leader in space exploration is still considered as essential to a majority of Americans (see Figure 3); * The dollars spent in each state, boosting economies throughout the entire nation(see...

Words: 906 - Pages: 4

Premium Essay

Micfrosoft and Google

...ASSIGNMENT-6 1. What are “rich Internet applications” and why are they important today? There has been a tremendous amount of attention on getting "back to the desktop" with technologies like Apollo and Windows Presentation Foundation that enable some very rich, design-friendly experiences outside the browser. But there is still a very large contingent out there that thinks the browser will be the best way to deliver applications. But if that is the case, then we have to have a model that enables the browser to actually do that. Trying to build real applications using JavaScript that requires a tedious development cycle and a lot of per-browser workarounds just isn't going to cut it. From Ted's point of view, that is what makes the idea of open source Flash so compelling (and important). We get all the richness and robustness of Flash, but in a platform that anyone can contribute to and help grow. 2. How can Appcelerator speed up the application development process? The birth of brilliant modern technology that can handle numerous applications on devices like Iphones, net books or Blackberries has created a sea of endless opportunities. Countless of application can and are being built right now all over the world. This is a long and hefty process and developers need a helping hand. That is where Appcelerator comes in. This a successful start-up from California which helps developers to efficientize their activity by cutting development time in half, driving down development...

Words: 2470 - Pages: 10

Premium Essay

Mary Jackson's Impact On The Twentieth Century

...Latoya Tanilus Mrs. Henderson American History/ Period 4 21 February 2017 Mary Jackson "Coming here from the South will be a culture shock. It is important for us to reach out and help them adjust." Mary Jackson. Mary had a love for science and a passion to help people that were surrounding her. Mary hometown was in Hampton, Virginia where there weren't many opportunities for black and especially for black women. "In the 1970a Mary help young children's that were in the science club and the "Hampton's King Street Community center to build their own tunnel vision and use it to do experiments." (Shetterly) Mary Jackson impacted the twentieth century in many positive ways. Mary set a path for women to go into the engineering field, and made...

Words: 607 - Pages: 3

Premium Essay

Space-X Business Strategy

...by former PayPal entrepreneur and Tesla Motors CEO Elon Musk. SpaceX was founded with the goal of reducing space transportation costs and enabling the colonization of Mars. It has developed the Falcon 1 and Falcon 9 launch vehicles, both of which were designed from conception to eventually become reusable. SpaceX also developed the Dragon spacecraft, which are flown into orbit by the Falcon 9 launch vehicle, initially transporting cargo and later planned to carry humans to the International Space Station and other destinations.[1] By 2012, SpaceX had over 40 launches on its manifest representing about $4 billion in contract revenue—with many of those contracts already making progress payments to SpaceX—with both commercial and government (NASA/DOD) customers. As of December 2013, SpaceX has a total of 50 future launches under contract, two-thirds of them are for commercial customers.  SpaceX's low launch prices, especially for communication satellites flying to geostationary orbit, have resulted in market pressure on its competitors to lower their own prices. In recent years, the communications satellites launch market has been dominated by "Europe's Arianespace, which flies the Ariane 5, and International Launch Services (ILS), which markets Russia's Proton vehicle." Depending on a number of factors, mostly the size and weight of payload, the cost of a single launch ranges from $100 million to $260...

Words: 8295 - Pages: 34

Free Essay

First Biz Paper

...Center is located in Huntsville, Alabama. The facility is one of the nation’s top science centers and is home to America’s Space Program. Huntsville, Alabama, is the birthplace of the US Space program and the Center is used as a location to help that story. More than 60 years ago, German Rocket scientists were moved to Huntsville following the end of World War Two. The US Army tagged their mission, “Operation Paperclip.” The Army used that name to describe more than 100 German scientists whose names were inside a folder. The materials were held together by a simple paperclip. The name stuck and became one of America’s greatest accomplishments as the Germans began working for the United States Army to develop missiles. At the end of World War Two, the Army allowed the German scientists to continue their work. Their dreams were not to create, build or deploy army rockets, but rather to create rockets that could go into space. In 1958, President Dwight D. Eisenhower created the agency under the name The National Aeronautics and Space Act. The NASA mission, according to President Eisenhower, was to encourage peaceful applications in space science. As the program grew, President Kennedy challenged the nation to go the moon in the decade of the 1960’s. In Kennedy’s words, “We choose not to do this because it is easy but because it is hard.” NASA, using more than 20 billion dollars in federal funding, began building the Saturn V rocket to take man to the moon. On July...

Words: 742 - Pages: 3

Free Essay

Ethics Report

...Ethics and Leadership Report Vincent Renda Applied Leadership - mgt331 Baker College Dr. Julia Teahen 3/28/16 Provide a brief summary of the movie you chose. Be sure to provide a description of each major character, their leadership style, and why you believe they were important to the story. Brief Summary Movie-APOLLO 13 NASA’s Apollo 13 mission was a mission to the moon, but because of mechanical problems the Apollo 13 not only failed to reach the moon, it was almost lost. The Apollo 13" mission showed men solving problems with their intelligence, their skill sets, bravery and most of all teamwork. This mission raised issues of loyalty for the individual against the loyalty of the team as a whole. It represented how the success of the mission became more important than the need of the one. Ken Mattingly one of the astronauts that was supposed to be on the Apollo 13 mission but was cut for a “maybe” health issue, played the role of the person who saved the mission. He showed that even with bad luck that prevented him from being on the mission, means even if you are not on the first team, you can still play the most important in saving the mission and become a hero. Each astronaut, was a positive male role model in their own right. (NASA, 2016). Major Characters Jim Lovell: Apollo 13 commander, was the world’s most traveled astronaut. He participated in three mission and had 572 hours of spaceflight experience. He demonstrated transformational...

Words: 2718 - Pages: 11

Premium Essay

Nasa Safety Culture

...NASA’s built a habit of relaxing safety standards to meet financial and time constraints. The agency’s “broken safety culture” would lead to tragedy again unless fundamental changes are made. NASA has made a critical mistake in its culture the space agency’s attitude toward safety hasn’t changed much since the 1986 Challenger disaster, which also killed seven along with the Columbian disaster. NASA lacks “effective checks back to the basics of understanding their operation and does not have an independent safety program and has not demonstrated the characteristics of a learning organization, NASA fell into the habit of accepting as normal some flaws in the shuttle system and tended to ignore or not recognize that these problems could foreshadow...

Words: 1582 - Pages: 7

Premium Essay

Evolving Concepts of Crew Resource Management

...Aeronautical University Evolving Concepts of Crew Resource Management The roots of Crew Resource Management training in the United States are usually traced back to a workshop, Resource Management on the Flightdeck sponsored by the National Aeronautics and Space Administration in 1979 (Cooper, Lauber, & White, 1980). This conference was the outgrowth of NASA research into the causes of air transport accidents. The research presented at this meeting identified the human error aspects of the majority of air crashes as failures of interpersonal communications, decision making, and leadership. At this meeting, the label Cockpit Resource Management (CRM) was applied to the process of training crews to reduce "pilot error" by making better use of the human resources on the flightdeck. Many of the air carriers represented at this meeting left it committed to developing new training programs to enhance the interpersonal aspects of flight operations. Since that time CRM training programs have proliferated in the United States and around the world. Approaches to CRM have also evolved in the years since the NASA meeting (Helmreich, Merritt, & Wilhelm, 2001). CRM training is now used by all the major international airlines. A recent survey of International Air Transport Association affiliated airlines indicated that 96 per cent of respondents were running CRM courses. Over 60 per cent of these had been in existence for five years or more (O'Leary, 1999). In Europe,...

Words: 1017 - Pages: 5

Premium Essay

Remington Peckinpaw Davis Generic Benchmarking Worksheet

...Remington Peckinpaw Davis Generic Benchmarking Worksheet |Task A: Problem/Opportunity Statement | |Instructions for Task A: In the Response row, write out the problem/opportunity statements for the scenario for each of the team | |members. | |Response to Task A: | |Betty - Remington Peckinpaw Davis will implement advanced technology and strategic performance management tools and techniques to | |manage cost, increase market share and maintain customer loyalty while remaining a leader in the online trading industry. | | | |Generic Benchmarking—The purpose of generic benchmarking is to identify potential solutions to the problem statements defined in Task | |A. You will do this by looking at how companies in other industries have dealt with similar issues. | |Topic A: Data Reliability | |Response to Topic A: ...

Words: 1642 - Pages: 7

Premium Essay

Aquisition

...assignment, review GAO Report titled, “Acquisition Planning: Opportunities to Build Strong Foundations for Better Services Contracts,” GAO-11-672, August 9, 2011, located at http://www.gao.gov/new.items/d11672.pdf. Write a four to five (4-5) page paper in which you: 1.Compare and contrast how the listed agencies, such as the Departments of Health and Human Services (HHS), Homeland Security (DHS), and the National Aeronautics and Space Administration (NASA), have carried out acquisition planning. The Departments of Health and Human Services (HHS), Homeland Security (DHS) and the National Aeronautics and Space Administration (NASA) have set requirements for acquisition planning to balance any oversights with time and administrative burden. These agencies require written acquisition plans that are closely aligned with the elements defined by the Federal Acquisitions Regulations (FAR). The establish guidelines state that cost estimates and requirements documents must be prepared during the acquisition planning. The guidelines for DHS and NASA include considerations of lessons from the experiences of previous contracts as part of the acquisition planning. Additionally, these agencies have set different requirements for who must review and approve acquisition planning documents, to avoid oversights (GAO, 2011) 2....

Words: 932 - Pages: 4

Premium Essay

Deep Space Exploration

...medical research. I, for one, feel that Humans should explore deep space, because there are huge benefits for exploring deep space. There are of course obstacles in the way of the benefits of deep space so, what is the price tag on a deep space flight? Is what will be gained be worth the price that tax payers spend? Cost is only part of the problem; NASA has not launched a rocket since the Saturn V rockets used to take astronauts to the moon. And has been seen in recent days, the space shuttles are an old technology and have been retired. Another daunting question is the moral implications of sending people into deep space since they have no idea what effects having a human child in space would have on the child itself nor what effects zero G would have on an expecting mother. How will NASA be able to get exploration vehicles into space? What is needed is a solution to these problems. They need to figure out a way to make space exploration to become affordable. They will need to figure out a way to not only bring in money but also how to make space missions affordable. There may be several ways that this can be accomplished. Also, NASA will need to start out small, perhaps by starting out with a moon colony to begin with and then move on to other planets such as Mars. I feel that deep space travel could be affordable partially through means of privatization. Private companies are already starting to experiment with the idea of selling tourist flights to space. The space tourism...

Words: 737 - Pages: 3

Premium Essay

Privatization of the Space Flight Program

...States Space Program has brought to life things that, as late as the 1950’s, were once believed to be impossible. As a little boy, I remember watching TV in the library at school as the latest space shuttle was going to blast off from its launch pad en route to its destiny in space exploration. As I’ve grown, so too has my never ending curiosity of what lies beyond our own planet and solar system. We have been to the moon, seen unbelievable, up close photos of planets like Mars, Jupiter, and Saturn, and just when it looked like we’re about to make a leap into exploring beyond our solar system or possibly sending a manned mission to Mars, it all stops. Along with millions of other people who grew up dreaming of one day going into outer space or visiting a faraway planet, we all watched in horror as the United States Space Program has all but been eliminated by decisions made by members of Congress and President Barak Obama to drastically overhaul funding for NASA and the United States Space Program. In 2010, the President announced dramatic changes including the abandonment of the Constellation program and the Ares Rocket which was supposed to replace the newly retired space shuttle program, as well as outlining the development of commercializing elements of the industry which has forced NASA to re-evaluate the overall direction of its program and establish new, long-term initiatives. Will the commercialization and privatization of the space flight program enable NASA and the Unites...

Words: 2089 - Pages: 9

Premium Essay

Nasa

...The Challenger- Nasa’s Decision MAking Process By Briana Bass Brianacbass@gmail.com Leadership & Organization Behavior MGMT-591-20623 John Poore 2/19/2015 The Challenger- NASA’s Decision Making Process Introduction: I am researching the decision making process that allowed on space shuttle, called the Challenger to go up into space, but was destroyed upon take off. I will analyze the reasons why NASA allowed this aircraft to take off, and the reason why it should not have. I will also research the aftermath and how this huge error could have been avoided. The National Aeronautics and Space Administration was created on October 1, 1958 by the President of the United States and Congress. It was to provide research into the problems of flight within and outside the Earth’s atmosphere. The main reason NASA was invented was due to World War 2. The United States and the Soviet Union were engaged in a cold ward. During this time, space exploration become the one of the highest priority discussions. This became known as the space race. (American Psychological Association, 2011) The United States launched its first Earth satellite on January 31, 1958. It was called Explorer 1. Then the United States started several missions to the moon and other planets in 1950 and the 1960’s. It had 8,000 employees and an annual budget of $100 million. Nasa rapidly grew. They had three main laboratories. First, Langley Aeronautical Laboratory, Second, Ames Aeronautical...

Words: 2518 - Pages: 11