Free Essay

Project Management Pert

In:

Submitted By Petemiller
Words 1617
Pages 7
Chapter 13 Project Management

Characteristics of a “project”:
■ A

project is unique (not routine), ■ A project is composed of interrelated sub-projects/activities, ■ It is associated woth a large investment.

What is Project Management
■ To

schedule and control the progress and cost of a project.

PERT/CPM:


Input:
– – –

Activities in a project; Precedence relationships among tasks; Expected performance times of tasks. The earliest finish time of the project; The critical path of the project; The required starting time and finish time of each task; Probabilities of finishing project on a certain date; ...



Output:
– – – – –

PERT/CPM is supposed to answer questions such as:
■ How

long does the project take? ■ What are the bottle-neck tasks of the project? ■ What is the time for a task ready to start? ■ What is the probability that the project is finished by some date? ■ How additional resources are allocated among the tasks?

PERT Network:
• • • •



It is a directed network. Each activity is represented by a node. An arc from task X to task Y if task Y follows task X. A ‘start’ node and a ‘finish’ node are added to show project start and project finish. Every node must have at least one outgoing arc except the ‘finish’ node.

Example of Foundry Inc., p.523
Activity A B C D E F G H Immediate Predecessors A B C C D, E F, G

PERT Network for Foundry Inc. Example

Example of a Hospital Project:
Activity
A B C D E F G H I J K

Immediate Predecessor(s)
— — A B B A C D A E, G, H F, I, G

PERT Network for Hospital Project

Performance Time t of an Activity
§

t is calculated as follows: a + 4m + b t = 6 where a=optimistic time, b=pessimistic time, m=most likely time.

§

Note: t is also called the expected performance time of an activity.

Variance of Activity Time t


If a, m, and b are given for the optimistic, most likely, and pessimistic estimations of activity k, variance σk2 is calculated by the formula σk 2

⎛ b − a ⎞ = ⎜ ⎟ ⎝ 6 ⎠

2

Variance, a Measure of Variation
■ Variance

is a measure of variation of possible values around the expected value. ■ The larger the variance, the more spreadout the random values. ■ The square root of variance is called standard deviation.

Example, Foundry Inc., p.525
Activity a m b t variance

A B C D E F G H

1 2 1 2 1 1 3 1

2 3 2 4 4 2 4 2

3 4 3 6 7 9 11 3

Critical Path
• • •

It is the “longest” path in the PERT network from the start to the end. It determines the duration of the project. It is the bottle-neck of the project.

Time and Timings of an Activity:
• • • • • •

t=estimated performance time; ES=Earliest starting time; LS=Latest starting time; EF=Earliest finish time; LF=Latest finish time; s=Slack time of a task.

Uses of Time and Timings
■ Earliest

times (ES and EF) and latest times (LS and LF) show the timings of an activity’s “in/out” of project. ■ ES and LS of an activity tell the time when the preparations for that activity must be done. ■ For calculating the critical path.

Computing Earliest Times
Step 1. Mark “start” node: ES=EF=0. Step 2. Repeatedly do this until finishing all nodes:
For a node whose immediate predecessors are all marked, mark it as below:
• •

ES = Latest EF of its immediate predecessors, EF = ES + t


Note: EF=ES at the Finish node.

Computing Latest Times:
Step 1. Mark “Finish” node:
LF = LS = EF of “Finish” node.

Step 2. Repeatedly do this until finishing all nodes:
For a node whose immediate children’s are all marked with LF and LS, mark it as below:
• •

LF = Earliest LS of its immediate children, LS = LF – t


Note: LS=LF at Start node.

Computing Slack Times


For each activity:
– slack

= LS – ES = LF – EF

Foundry Inc. Example


Calculate ES, EF, LS, LF, and slack for each activity of the Foundry Inc. example on its PERT network, given the data about the project as in the next slide.

Example, Foundry Inc.
Activity a m b t variance

A B C D E F G H

1 2 1 2 1 1 3 1

2 3 2 4 4 2 4 2

3 4 3 6 7 9 11 3

2 3 2 4 4 3 5 2

0.111 0.111 0.111 0.444 1 1.777 1.777 0.111

A
ES= LS=

2
EF= LF=

C
ES= LS=

2
EF= LF=

F
ES= LS=

3
EF= LF=

slack=

slack=

slack=

Start
ES=EF= LS=LF=

E
ES= LS=

4
EF= LF=

H
ES= LS=

2
EF= LF=

Finish
ES=EF= LS=LF=

slack= B
ES= LS=

slack= G
ES= LS=

3
EF= LF=

D
ES= LS=

4
EF= LF=

5
EF= LF=

slack=

slack=

slack=

Network for Foundry Inc.

Example of Hospital Project:
■ Calculate

ES, EF, LF, LS and slack of each activity in this project on its PERT network, given the data about the project as in the next slide.

Example: A Hospital Project
Activity
A B C D E F G H I J K

Immediate Predecessor(s)
— — A B B A C D A E, G, H F, I, G

Performance time t (weeks)
12 9 10 10 24 10 35 40 15 4 6

F
ES=

10
EF= LF=

A
ES= LS=

12
EF= LF=

LS=

K
ES= LS=

6
EF= LF=

slack= I
ES= LS=

15
EF= LF=

slack=

slack=

slack= Start
ES=EF= LS=LF=

G 10
EF= LF= ES= LS=

35
EF= LF=

C
ES= LS=

Finish
ES=EF= LS=LF=

slack=

slack= D B
ES= LS=

10
EF= LF=

H
ES= LS=

40
EF= LF=

9
EF= LF=

ES= LS=

J
ES= LS=

4
EF= LF=

slack= E
ES= LS=

slack= 24
EF= LF=

slack=

slack=

slack=

A Hospital Project

Slack and the Critical Path
• •

The slack of any activity on the critical path is zero. If an activity’s slack time is zero, then it is must be on the critical path.

Critical Path, Examples


What is the critical path in the Foundry Inc. example? What is the critical path in the Hospital project example?



Calculate the Critical Path:
Step 1. Mark earliest times (ES, EF) on all nodes, forward; Step 2. Mark latest times (LF, LS) on all nodes, backward; Step 3. Calculate slack of each activity; Step 4. Identify the critical path that contain the activities with zero slack.

C
ES= LS=

4
EF= LF=

A
ES= LS=

2
EF= LF=

slack=

slack= Start
ES=EF= LS=LF=

D
ES= LS=

3
EF= LF=

Finish
ES=EF= LS=LF=

slack= B
ES= LS=

7
EF= LF=

E
ES= LS=

2
EF= LF=

slack=

slack=

Calculate the critical path

Example: Draw diagram and find critical path Activity A B C D E F G H I Predecessor B A C A,D E,G G t 5 3 6 4 8 12 7 6 5

Example: Draw diagram and find critical path Activity A B C D E F G H Predecessor A B A,B C D,E,F E,F t 3 4 6 5 8 2 4 5

Solved Problem 13-1&2, p.547-548

Calculate the Critical Path
Activity A B C D E F G a 1 2 4 8 2 4 1 m b 2 3 3 4 5 6 9 10 5 8 5 6 2 3 Immediate predecessor A B C, D B E

Steps for Solving 13-1&2
1. 2. 3. 4.

Calculate activity performance time t for each activity; Draw the PERT network; Calculate ES, EF, LS, LF and slack of each activity on PERT network; Identify the critical path.

Probabilities in PERT




Since the performance time t of an activity is from estimations, its actual performance time may deviate from t; And the actual project completion time may vary, therefore.

Probabilistic Information for Management
■ The

expected project finish time and the variance of project finish time; ■ Probability the project is finished by a certain date.

Project Completion Time and its Variance


The expected project completion time T: T = earliest completion time of the project. The variance of T, σT2 : σT2 = Σ(variances of activities on the critical path)



Example, Foundry Inc.
Activity a m b t variance

A B C D E F G H

1 2 1 2 1 1 3 1

2 3 2 4 4 2 4 2

3 4 3 6 7 9 11 3

2 3 2 4 4 3 5 2

0.111 0.111 0.111 0.444 1 1.777 1.777 0.111
Variance of T, σT2 =

Critical path: A-C-E-G-H Project completion time, T =

Solved Problem 13-1&2, p.547-548

Project completion time and variance
Activity A B C D E F G a 1 2 4 8 2 4 1 m 2 3 5 9 5 5 2 b 3 4 6 10 8 6 3 t 2 3 5 9 5 5 2 variance 0.111 0.111 0.111 0.111 1 0.111 0.111

Critical path: B-D-E-G Project completion time, T = Variance of T, σT2 =

Probability Analysis


To find probability of completing project within a particular time x:
1. Find the critical path, expected project completion time T and its variance σT2 .
2. Calculate Z = x −T

σT 2

3. Find probability from a normal distribution table (as on page 698).

The Idea of the Approach




The table on p.698 gives the probability P(z

Similar Documents

Premium Essay

Chanii

...Overview Project Management for IT professionals includes planning, scheduling, monitoring, and controlling, and reporting on information system development. History Wendy Lee, manager of college services at Mountain View Colleges wants a new information system that will improve efficiency and costume service at the three college bookstores. Description of the Process Project planning, Gantt Charts, PERT/CPM Charts, Microsoft Project and Open Workbench software, project monitoring, and risk management techniques. Important terms and Concepts What Does Project Manager Do? Whether a project involves a new office building or an information system, good leadership is essential. In systems project, the project manager, or project leader, usually is a senior systems analyst or an IT department manager if the project is large. What is a Gantt chart? A Gantt chart was design that could show planned and actual progress on a project. A Gantt Chart is horizontal bar chart that represents a set of tasks. What is a PERT/CPM Chart? The Program Evaluation Review Technique (PERT) is a bottom-up technique, because it analyzes a large, complex project as a series of individual tasks. At approximately the same time, the CPM (Critical Path Method) meet similar project management needs. The distinction between the two methods has disappeared over time, and today the technique is called either PERT, CPM, or PERT/CPM. Maintaining a Schedule A project schedule can be challenging, and...

Words: 486 - Pages: 2

Premium Essay

Quantitative Analysis Tools for Managers

...on Software tools available for project management to help managers to use quantitative analysis Project Management: A project is temporary in that it has a defined beginning and end in time, and therefore defined scope and resources. And a project is unique in that it is not a routine operation, but a specific set of operations designed to accomplish a singular goal. So a project team often includes people who don’t usually work together – sometimes from different organizations and across multiple geographies. The development of software for an improved business process, the construction of a building or bridge, the relief effort after a natural disaster, the expansion of sales into a new geographic market — all are projects. And all must be expertly managed to deliver the on-time, on-budget results, learning and integration that organizations need. Project management, then, is the application of knowledge, skills and techniques to execute projects effectively and efficiently. It’s a strategic competency for organizations, enabling them to tie project results to business goals — and thus, better compete in their markets. Microsoft Project has a qualitative risk analysis methodology capability But what about quantitative cost and schedule risk analysis? Quantitative risk analysis gives the project manager the ability to see how a project schedule will be affected if project risks become issues. As a result of this insight, project managers is implement risk responses...

Words: 2624 - Pages: 11

Premium Essay

Busn310 Letman

...Madigan Army Medical Facility Marva M. White American InterContinental University March 11, 2012 Introduction All medical facilities as well as other organization have s specific purpose in mind when selecting certain areas in which to conduct their business. The Madigan family has seen a lot of military service. Four generation has served, suiting up for the major conflicts for the past century. Madigan gets its name from Retired Colonel John J. Madigan III, who died May 4, 2009, at the age of 80. His daughter stated her dad will be remembered for being passionate about the Army, his Family, his teachings and Washington Redskins. By March 2, 1992, a new medical facility was constructed, dedicated to Colonel Madigan, by naming the 245 bed facility after him. His legacy remains, and the Madigan family still to this day, because of what he believed in, lives by this motto, “Compassion with Care” for all military and their families who has to be seen in our modern and up-to-date technology facility with the upmost quality care. This is a facility that serves all branches of the military being, the Army, Air Force, Navy, Marines, active duty military, reserves, retirees, veterans and their families. Maj. Gen. Richard Thomas, former assistant surgeon general for Force assumed his command for the Western Regional Medical Command, March 7, 2011, during a change of command held on the facility grounds. Madigan is well aware with environmental issues ,which takes...

Words: 2356 - Pages: 10

Premium Essay

Cpm and Pert

...of CPM Project Planning ……….……………………………………………………………………………… 9 2.2.2 Example of CPM …………………………………………………………………………………………………………… 11 2.2.3 Benefits of CPM …………………………………………………………………………………………………………… 12 2.2.4 Limitation of CPM …………….…………………………………………………………………………………………. 12 2.3 Project Evaluation and Review Techniques (PERT) ……..……………..………………………………………… 13 2.3.1 Steps of PERT in Project Planning ……....……………………………………………………………………….. 14 2.3.2 Benefits of PERT……..……………………………………………………………………………………………………. 16 2.5.1 Limitation of PERT ……………………………………………………………………………………………………….. 16 3.0 CONCLUSION 17 4.0 REFERANCES 29 1.0 INTRODUCTION: 1.1 What is a project? A project is a series of activities directed to accomplishment of a desired objective. A project have a defined start which is when the descision of the project process starts and also a defined end where by that point the goal and the objectives of that project is achived. 1.2 What is project management? Project management its concerned with the overall planning and co-ordination of a project from conception to completion aimed at meeting the stated requirements and ensuring completion on time, within cost and to required quality standards. Project management is normally reserved for focused, non-repetitive, time-limited activities with some degree of risk and that are beyond the usual scope of operational activities for which the organization is responsible. 1.3 Project management steps: ...

Words: 2946 - Pages: 12

Premium Essay

Pert, Gantt Charts and Work Breakdown Structure

...The PERT Chart Program Managers often utilize tools such as, the Program Evaluation and Review Technique or PERT charts. PERT charts help managers with planning the schedule of projects that involve sequential activities. A PERT chart identifies the amount of time that is required to complete the activities in a project, and the order of the steps that occurs throughout the project. Each activity is assigned an earliest and latest start time and end time; activities with no slack time are said to lie along the critical path, this is the path that must stay on time for the project to stay on schedule (Ingram, 2013). One of the strengths that the PERT charts have is their ability to calculate exactly how long a project will take. They provide managers with a range of time in which the project should be completed, based on the total of all the minimum and maximum time limits for all of the activities. This gives companies a number of advantages, such as the ability to tell their customers exactly when their orders will be filled, or exactly when they should order new supplies. One weakness a PERT chart has is that it does not take into account the possibility of unexpected occurrences. The expected completion time of all subsequent activities and the project as a whole can get off track when things go wrong, which can cause problems if the company has made plans that rely on the timely completion of the project. Another weakness of PERT chart is that the technique relies...

Words: 1000 - Pages: 4

Premium Essay

Deqwe

...MSP 10 Project Management with PERT/CPM One of the most challenging jobs that any manager can take on is the management of a large-scale project that requires coordinating numerous activities throughout the organization. A myriad of details must be considered in planning how to coordinate all these activities, in developing a realistic schedule, and then in monitoring the progress of the project. Fortunately, two closely related operations research techniques, PERT (program evaluation and review technique) and CPM (critical path method), are available to assist the project manager in carrying out these responsibilities. These techniques make heavy use of networks (as introduced in the preceding chapter) to help plan and display the coordination of all the activities. They also normally use a software package to deal with all the data needed to develop schedule information and then to monitor the progress of the project. Project management software, such as MS Project in your OR Courseware, now is widely available for these purposes. PERT and CPM have been used for a variety of projects, including the following types. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Construction of a new plant Research and development of a new product NASA space exploration projects Movie productions Building a ship Government-sponsored projects for developing a new weapons system Relocation of a major facility Maintenance of a nuclear reactor Installation of a management information system Conducting an advertising...

Words: 27582 - Pages: 111

Premium Essay

Project Management

...Project Management 1. Introduction As a discipline and professional subject, project management has gained unprecedented prevalence throughout the world as a consequence of its role in assisting the organization to efficiently utilize limited resources, resolving sophisticated technology and enhancing its survive in the increasingly competitive market. Specifically, implementing project management techniques assists the organization in curtailing the overheads costs, satisfying project deadlines and customizing the project workplace and so forth. Some 4500 years ago, projects had been undertaken with the pyramids construction by the ancient Egyptians, but it is universally accepted that the period of 1950s is an indication of the arrival of modern management era and the commencement of utilizing formal project management tools and techniques (Awan, 2010). Economic pressures of the industrialized world, competition between rival companies and greater regard for the value, well-being and hence the employment costs of working people have all contributed to the development of new project management ideas and techniques. The purpose of this essay is to identify the major developments in the domain of project management over the past five decades and to explain how these historical developments influence the understanding of modern project management. 2. Crucial Developments in the Field of PM and Repercussions on Understanding Modern Project Management Prior to 1950s...

Words: 2234 - Pages: 9

Premium Essay

Project Management Analysis

...Project Management analysis BUSN300-1201B- Abstract Some form of Project Management is done in all types of businesses. According to Project Management Institute (2012), Project Management is when an individual applies the knowledge, techniques, and skills to accomplish a project effectively and efficiently with an ultimate goal in mind. This paper will analyze managerial, operational, and financial issues. This paper will also explore project management, project timelines, and contingency planning. Staffing needs will be explored, and an example of a Gantt and PERT chart will be included. Project Management analysis According to Project Management Institute (2012), Project Management is when an individual applies the knowledge, techniques, and skills to accomplish a project effectively and efficiently with an ultimate goal in mind. The goal of project management would be to make sure that the project is done in a timely manner, and under or right at budget. A project manager’s also has to understand scheduling, and how to head off any critical paths that may come in the way. And the best way to do that is by tracking information about the project on charts. The best charts to use to track information on a huge project would be the PERT and Gantt charts. According to The Constructor (2012), PERT stands for Program Evaluation and Review Technique. The PERT chart shows important information about the project. The chart is graph that has drawings on it that...

Words: 915 - Pages: 4

Premium Essay

Pert & Cpm

...CPM/PERT Presented by DATE- 08 Aug. 2014 Shravan Kumar Project  “A project is a series of activities directed to accomplishment of a desired objective.” Plan your work first…..then work your plan Network analysis Introduction Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. One definition of a project: “A project is a temporary endeavour undertaken to create a "unique" product or service”  History   Developed in 1950’s CPM by DuPont for chemical plants PERT by U.S. Navy for Polaris missile CPM was developed by Du Pont and the emphasis was on the trade-off between the cost of the project and its overall completion time (e.g. for certain activities it may be possible to decrease their completion times by spending more money how does this affect the overall completion time of the project?) PERT was developed by the US Navy for the planning and control of the Polaris missile program and the emphasis was on completing the program in the shortest possible time. In addition PERT had the ability to cope with uncertain activity completion times (e.g. for a particular activity the most likely completion time is 4 weeks but it could be anywhere between 3 weeks and 8 weeks). CPM - Critical Path Method  Definition: In CPM activities are shown as a network of precedence relationships using activity-on-node network construction – Single estimate of activity time – Deterministic...

Words: 947 - Pages: 4

Premium Essay

Pert and the Critical Path Method

...SIMILARITIES AND DIFFERENCES BETWEEN (PERT) AND (CPM) Critical Path Analysis and PERT are powerful tools that help you to schedule and manage complex projects. They were developed in the 1950s to control large defense projects, and have been used routinely since then. Program (Project) Evaluation and Review Technique (PERT) is a project management tool used to schedule, organize, and coordinate tasks within a project. It is basically a method to analyze the tasks involved in completing a given project, especially the time needed to complete each task, and to identify the minimum time needed to complete the total project. The Critical Path Method or Critical Path Analysis, is a mathematically based algorithm for scheduling a set of project activities.Critical path method seeks to determine the longest possible continuous pathway taken from the initial event to the terminal event. It determines the total calendar time required for the project; and, therefore, any time delays along the critical path will delay the reaching of the terminal event by at least the same amount. PERT Networks and CPM Arrow Diagramsare similar in manyways and yet take paths that are often-different:Both aresystematic ways of analyzing and planningthe components ofa program or project.Both have been used extensively byindustry and government. CPM uses activity oriented network while PERT uses event oriented network. Furthermore durations of an activity may be estimated with a fair degree of accuracy...

Words: 285 - Pages: 2

Premium Essay

Performance Measurement

...invest time, money, and resources in projects with the goal of earning a return on investment. The project manager ensures projects stay on schedule and within budget and performance management gives the project manager visibility to ensure they are operating within the agreed upon time and cost constraints and that the project is performing according to plan. Performance measurement is important because it is the process an organization uses to establish parameters to reach desired results (Schied, 2010). Measuring project performance allows the project manager to identify cost and schedule problems and take action to remedy problems quickly. Measuring project performance also provides the organization with a picture of how healthy the project is and can help establish improvement initiatives. When managing a project, triple constraints of budget, time, and performance are important measures. The budget is managed by controlling resources according to the financial plan of the project. Time keeps the team on schedule and allows meeting of deadlines. Performance measurements should be created by project and be based on the scope, goals, and objectives of the stakeholders (Schied, 2010). Measurements are specific to each project but three measurements that could be used to measure performance include speed, accuracy, and volume. Speed shows the rate of movement of the production process or final product made during the project and shows the pace at which the final...

Words: 834 - Pages: 4

Premium Essay

Essay

...Project Management Section A Part One: 1. Liquidation value of the firm’s assets could be considered as … a. The minimum wealth of shareholders 2. If ‘P’ be the initial investment, ‘I’ be the interest rate and ‘T’ be the time period for which funds are invested then interest earned will be … d. P*I*T 3. Following the above given conditions, compound interest is given by … b. P*(1+I)T 4. Firms resorting to “Proactive Growth” a. do constant strategic planning 5. SPACE stands for Strategic Position and Action Evaluation 6. Increasing market expenditure heading to an increased market share is known as … c. market expansion 7. If profit after tax is ‘A’, depreciation be ‘B’ and interest be ‘I’, then Interest cover ratio is given by 8. E-V rule is also called … 9. In case of internally generated funds the opportunity cost to the firm is … b. the lending rate 10. ‘PERT’ stands for Program Evaluation and Review Technique. Part Two: 1. Write a note on ‘Sinking Fund Payment’. Answer: A sinking fund is a means of repaying funds that were borrowed through a bond issue. The issuer makes periodic payments to a trustee who retires part of the issue by purchasing the bonds in the open market. Rather than the issuer repaying the entire principal of a bond issue on the maturity date, another company buys back a portion of the issue annually and usually at a fixed par value or at the...

Words: 1834 - Pages: 8

Premium Essay

Project Leadership

...Project management Name: Institution: Course: Tutor: Date of submission: Introduction to project management Program Evaluation and Review Technique This is simply the project managing method which in turn gives the time used by each factor of a project, and the amount of time needed for it to be finished. PERT tends to divide the project keen on activities and events that should be done. It comes up with a sequence which revolves around associations, and period in a structure of network. Basically the lines that are used in the link of the events are called paths, and also there is the longest path of connection that is linked with all the events which is known as the critical path. When looking at the span of the critical path, it is also the particular time a project will take in that order. If by any chance there is a delay of any kind, it will also delay the entire project. In conclusion PERT is a scheduling tool and it is not used in the lookout of the best or shortest methods of completion of any given project. (Baca, 2008). Critical Path Method This is a gradually method used in process planning. It gives account of the critical and also the non- critical duties basing on the aim of avoiding time casing troubles and method bottlenecks. The CPM is mainly placed to projects that are attached to various activities which are widely related. Some of the steps that can be used in the application of the CPM include the definition of the task at hand and writing them...

Words: 946 - Pages: 4

Premium Essay

Network Paper

...Network Management Systems Doniel Lovely NetW420: Enterprise Network Management Professor: Winston Park Devry University Date: 6/23/2013 Effectiveness and efficiency can at the same time or simultaneously perform at high standards in any given business organization. While effectiveness refers to the levels at which any organization realizes its goals through managing to accomplish set tasks, efficiency is highly related to the magnitude of resources utilized to achieve these goals of the organization. (Daft and Lane, 2008) This is a report set to answer the question, “Which are the various metrics used to measure the effectiveness and efficiency of a network in pursuit of organizational goals?” The report will answer in a detailed manner this aforementioned question. In PERT, the requirement is that each activity should be provided with three kinds of estimates. These are: Optimistic, Pessimistic and most likely times. Under the PERT procedure, the optimistic time denotes the shortest duration an activity can take to complete (pert.com, 2013). Commonly, to determine the Optimistic time three standard deviations are utilized to reduce the level of error in calculating the times. Pessimistic time on the other hand is the longest duration an activity may take to finish. Also, here three standard deviations are applied from the expected time. The Most likely time is the highest probability that an activity will be through in a given set time. However, this is not the same...

Words: 651 - Pages: 3

Premium Essay

Business Information

...engineering projects were generally managed by creative architects, engineers, and master builders themselves, for example Vitruvius (first century BC), Christopher Wren (1632–1723), Thomas Telford(1757–1834) and Isambard Kingdom Brunel (1806–1859).[8] It was in the 1950s that organizations started to systematically apply project management tools and techniques to complex engineering projects.[9] Henry Gantt (1861–1919), the father of planning and control techniques As a discipline, project management developed from several fields of application including civil construction, engineering, and heavy defense activity.[10] Two forefathers of project management are Henry Gantt, called the father of planning and control techniques,[11] who is famous for his use of the Gantt chart as a project management tool (alternatively Harmonogram first proposed by Karol Adamiecki[12]); and Henri Fayol for his creation of the five management functions that form the foundation of the body of knowledge associated with project and program management.[13] Both Gantt and Fayol were students of Frederick Winslow Taylor's theories of scientific management. His work is the forerunner to modern project management tools including work breakdown structure (WBS) and resource allocation. The 1950s marked the beginning of the modern project management era where core engineering fields come together to work as one. Project management became recognized as a distinct discipline arising from the management discipline...

Words: 613 - Pages: 3