Premium Essay

Project Process 4

In:

Submitted By Denver1234
Words 439
Pages 2
ORGANIZATIONAL STRUCTURE

The ownership of the company will purely reside with the funding company called Paarl Coldset. Although we only had preliminary discussions on ownership we are sure that ownership will maybe in the near future be divided between all involved in the process of the new business venture. The organization will be run by top management on behalf of Paarl Coldset just to make the day-to-day business flow. Managerial functions of the project will stop at the Plant manager and Administration department. All other functional departments on the lower level will be responsible for production on a day-to-day basis. The diagram below shows the proposed organizational structure.

Fig 1: Outline of Organizational Structure handeling the project

Paarl Coldset
Project Director
D Le Fleur
Plant Manager
L Mhlongo
Administrator
Z Mangcola
Supervisor 1
A Nkonyeni
Supervisor 2
S Ketani
Sorters

Technicians

Paarl Coldset
Project Director
D Le Fleur
Plant Manager
L Mhlongo
Administrator
Z Mangcola
Supervisor 1
A Nkonyeni
Supervisor 2
S Ketani
Sorters

Technicians

Fig 2: Interface between Project Structure and Operational Structure

Funding of Project
Funding of Project

Paarl Coldset
Project Director
D Le Fleur
Plant Manager
L Mhlongo
Administrator
Z Mangcola
Supervisor 1
A Nkonyeni
Supervisor 2
S Ketani
Sorters

Technicians

Paarl Coldset
Project Director
D Le Fleur
Plant Manager
L Mhlongo
Administrator
Z Mangcola
Supervisor 1
A Nkonyeni
Supervisor 2
S Ketani
Sorters

Technicians

Managerial Functions of Project
Managerial Functions of Project

Production Functions of Project
Production Functions of Project

Our Project Organization is based on grouping people together with a common goal and mission. Because our has a starting point and a termination point this project structure will

Similar Documents

Premium Essay

Relocation Project Fro Lab Equipment

...Relocation Project Project Management Plan (PMP) For ABC QC Lab Equipment Relocation * * May 4, 2010 Prepared by Ingrid Valmes Table of Contents 1. Introduction 1 1.1 Project Summary 1 1.1.1 Scope 1 1.1.2 Funding Source 1 1.1.3 Objectives 1 1.1.4 Products Produced by the Project 1 1.2 Document Summary 1 1.2.1 Purpose 2 1.2.2 Evolution of the Plan 2 2. Roles and Responsibilities 3 2.1 External Roles and Responsibilities 4 2.1.1 Project Sponsor 4 2.1.2 Resource Manager 4 2.1.3 Contracts Representative 4 2.2 Project Roles and Responsibilities 4 2.2.1 Senior Manager 4 2.2.2 Project Manager 4 2.2.3 Requirements Manager (Project Team Member) 4 2.2.4 Measurement Analyst (Project Team Member) 4 2.2.5 Quality Assurance Manager (Project Team Member) 4 2.2.6 Configuration Manager (Project Team Member) 4 2.2.7 Risk Manager (Project Team Member) 4 2.2.8 Team Leaders (Project Team Member) 4 2.2.9 Project Training Needs 4 3. Project Management Activities 4 3.1 Integrated Project Management 4 3.1.1 Use of DHI’s Defined Processes 4 3.1.2 Coordinate and Collaborate with Relevant Stakeholders 4 3.2 Project Planning 4 3.2.1 Establish Estimates 4 3.2.1.1 Material Costs 4 3.2.2 Develop a Plan 4 3.2.3 Obtain Commitment to the Plan 4 3.2.4 Communicate the Plan 4 3.2.5 Risk Management Planning 4 3.2.6 Quality Assurance Planning 4 3.2.7 Quality Assurance Audit Schedule 4 3.2.8 Project Management Tools 4 3.3 Project Monitoring and Control 4 3.3.1...

Words: 4534 - Pages: 19

Premium Essay

Project Management Outline

...PROJECT MANAGEMENT MODERN PROJECT MANAGEMENT 1. Define a project 2. Identify the stages involved in s project life cycle 3. Determine the roles of a project manager 4. Explain the importance of project management ORGANIZATION STRATEGY AND PROJECT SELECTION 1. Understand the strategic management process and the four activities involved at such 2. Define and explain the need for an effective project portfolio management system 3. Identify the classifications of a project 4. Identify sources and solicitation of project proposals 5. Rank proposals and select projects 6. Explain how to effectively manage a portfolio system in terms of risks and types of projects ORGANIZATION: STRUCTURE AND CULTURE 1. Determine the different project management structures 2. Identify the different ways to organize projects 3. Explain the essence of right project management in terms of both organizational considerations and project considerations 4. Explain organizational culture and justify its implications to organizing projects DEFINING THE PROJECT 1. Identify the different steps involved in defining a project 2. Understand process breakdown structure 3. Explain the responsibility matrices 4. Understand project communication plan ESTIMATING PROJECT TIMES AND COSTS 1. Identify the factors influencing the quality of estimates 2. Understand estimating guidelines for times, costs and resources 3. Compare between top-down and bottom-up estimating 4. Determine the methods...

Words: 819 - Pages: 4

Premium Essay

Management vs Leadership

...Section 4 Project Execution Phase 4.1 Project Execution Phase Overview Once a project moves into the Execution Phase, the project team and the necessary resources to carry out the project should be in place and ready to perform project activities. The Project Plan should have been completed and baselined by this time as well. The project team and specifically the Project Manager’s focus now shifts from planning the project efforts to participating in, observing, and analyzing the work being done. Figure 4.1.1 shows where in the Project Management the Execution Phase occurs. Figure 4.1.1 Project Management Execution Phase Project Manager’s Responsibilities A Project Manager’s responsibilities do not stop once the planning of the project is done. Because a Project Manager is responsible to internal and external stakeholders, the project team, vendors, executive management, etc. the visibility of the position is intensified. Many of these Project Management Methodology 4-1 Section 4 Project Execution Phase people will now expect to see and discuss the resulting deliverables that were so meticulously detailed in the Planning Phase. As a Project Manager, keeping oneself from getting “down in the weeds,” especially on large projects, will be important during project execution. This will allow the Project Manager to focus their attention on enabling the project plans, processes and managing the expectations of customers and stakeholders. Particular attention during...

Words: 3341 - Pages: 14

Premium Essay

Introduction to Testing

...Managing a Testing Project: (A White Paper) A White Paper Page 1 of 20 Vinod Kumar Suvarna IBM, Bangalore A White Paper Introduction Testing is expected to consume 30 – 50 % of the Project Effort, Still properly managing testing project is not considered seriously. Project Managers always undermine the impact the testing activity has on the Project Cost and Schedule. Hence the testing activity is usually unplanned and uncontrollable. As the project manager assumes that the main focus of the testing activity in the project is not to meet the project schedule. But Its is a reality that a thorough and close monitoring of the Testing project is required to increase productivity, reduce cycle -time and improve quality. Below pie chart depicts the Project effort distribution by phase for a development project, where independent testing team performs the testing activity. Project Effort Distribution by Phase 21 35 Requirement Design Code & Unit testing Testing 25 19 A White Paper Page 2 of 20 Vinod Kumar Suvarna IBM, Bangalore A White Paper The Problem / Issues / Improvement Opportunity in Hand: Ask a Tester ‘Why he/she needs to burn midnight oil to churn a Quality Product?’ Answer is obvious ‘Needs to put extra time and effort to overcome the Project schedule slippage ‘ Ask a Project Manager ‘Why the Project is in trouble during the last phase?’ Answer is obvious ‘Not Sure, Did not anticipate the dynamic changes effecting the Project’ The White...

Words: 2954 - Pages: 12

Premium Essay

Project Mgmt

...Project Management Institute A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK® Guide)—Fourth Edition 30, 0HPEHU &RS\ ² 1RW IRU 5HSURGXFWLRQ RU 'LVWULEXWLRQ An American National Standard ANSI/PMI 99-001-2008 ISBN: 978-1-933890-51-7 Published by: Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA. Phone: +610-356-4600 Fax: +610-356-4647 E-mail: customercare@pmi.org Internet: www.pmi.org ©2008 Project Management Institute, Inc. All rights reserved. “PMI”, the PMI logo, “PMP”, the PMP logo, “PMBOK”, “PgMP”, “Project Management Journal”, “PM Network”, and the PMI Today logo are registered marks of Project Management Institute, Inc. The Quarter Globe Design is a trademark of the Project Management Institute, Inc. For a comprehensive list of PMI marks, contact the PMI Legal Department. PMI Publications welcomes corrections and comments on its books. Please feel free to send comments on typographical, formatting, or other errors. Simply make a copy of the relevant page of the book, mark the error, and send it to: Book Editor, PMI Publications, 14 Campus Boulevard, Newtown Square, PA 19073-3299 USA. To inquire about discounts for resale or educational purposes, please contact the PMI Book Service Center. PMI Book Service Center P.O. Box 932683, Atlanta, GA 31193-2683 USA Phone: 1-866-276-4764 (within the U.S. or Canada) or +1-770-280-4129 (globally) Fax: +1-770-280-4113 E-mail: book.orders@pmi.org Printed in the...

Words: 148336 - Pages: 594

Premium Essay

Project Management Summary

...into outputs Process ! activity(s) that transforms inputs into outputs Operation ! group of resources performing one or more processes Functional Areas of business (acquires!fin.!Resources&capital! for!input)! Finance* Material!&! Service! Inputs! Operations* (material!&!service!into! outputs)! !!!!!!!!!!!!!!Support!Functions! ! • Accounting! • Information!System! • HR! • Engineering! Product!&! Service! Output! Marketing* Sales! Revenue! (Generates!sales!of!output)! • • Process and Operations are influences by internal and external customers considering feedback Two types of Process ! Manufacturing and Service Manufacturing Physical output Can be inventoried Low customer contact Long response time Capital intense Quality easily measured Service Intangible output Cannot High Short Labor intense Not easily measured Core Process (within the Supply Chain) ! Set of activities delivering value to external customers 1. Supplier Relationship Process ! selects suppliers & facilitates flow of items into firm 2. New Service/Product Development Process ! designs & develops new S/P received from inputs received from ext customer specifications or from mkt in general (through Customer Rltnshp Process) ! 1! 3. Order Fulfillment Process ! activities required to produce and deliver S/P to external customer 4. Customer Relationship Process ! identifies, attracts & builds rltnshp with customer & facilitates placement of orders • • Support Process ! provides vital...

Words: 12516 - Pages: 51

Premium Essay

Financial Management

...[pic] Financial Management Process© For [Project Name] 1 Introduction The Project Financial Management Process is followed after the initial project budget has been documented and approved during the Project Initiation phase of the Project Management Life Cycle. What is a Financial Management Process? A Financial Management Process is a method by which costs (or expenses) incurred on the project are formally identified, approved and paid. Typical types of costs include: • Labor (e.g. staff, external suppliers, contractors and consultants) • Equipment (e.g. computers, furniture, building facilities, machinery and vehicles) • Materials (e.g. stationery, consumables, building materials, water and power) • Administration (e.g. legal, insurance, lending and accounting fees). © When to use a Financial Management Process The Financial Management Process should be initiated after the expected Financial Expense Form has been created and approved during the Planning phase of the project. This process provides a mechanism for monitoring and controlling the actual financials of the project against those that were originally planned/budgeted. It important to formally track expenses throughout all phases of the project, otherwise, it may become impossible to accurately manage the project constraints of time, budget and quality. 1.1 Instructions Complete all sections of this form. If a particular section is...

Words: 1546 - Pages: 7

Premium Essay

Volkswagen

... each with a different ELT member. The results of a new prioritization process—a list of IT projects that would be funded in 2004—had been unveiled only a few days earlier. But already a storm was gathering. The phone calls from other executives had common themes. All the callers had expressed concern that high priorities for their areas of the company had not been funded. Some had repeated views expressed during the prioritization process by people who worked for them about supposed categorization mistakes that penalized their business units. And each of the calls had concluded with an informal request to insert an unfunded project (or two) into the IT department’s work plans. “We don’t have to reopen the process,” the most recent caller had said, “but perhaps spare capacity might be applied to make some progress on this project in 2004—we’ve done this before, and it would mean a lot to our area and to the company’s growth plans.” The 10 business units that made up VWoA had proposed more than 40 projects, with funding requirements totaling $210 million (US). A budget of only $60 million (an amount capped by VWAG, the parent company of VWoA) made some degree of disappointment inevitable. But the intensity of pushback against the new process was surprising. The ELT had endorsed the idea of improving upon the old way these decisions were made, via unstructured debate among executive sponsors. The new process, it was agreed, would...

Words: 6266 - Pages: 26

Premium Essay

Etihad Airways

...1. 1. Approximately what percentage of the wortd's gross domestic product is spent on projects? a. 10 percent b. 25 percent c. 50 percent d. 75 percent b. 25 percent 2. 2. Which ofthe following is a I'IOt a potential advantage of using good projectmanagement?a. Shorter developmenttimesb. Higher workermoralec. Lower cost of capitald. Higher profitmargins c. Lower cost of capital 3. 3. A ___ is a temporary endeavor undertaken to create a unique product, service, or result. a . program b process c. project d . portfolio c. project 4. 4. Which of the following is not an attribute of a project? a. projects are unique b. projects are developed using progressive elaboration c. projects have a primary customer or sponsor d. projects involve little uncertainty d. projects involve little uncertainty 5. 5. Which of the following is not part of the triple constraint of project management? a. meeting scope goals b. meeting time goals c. meeting corrmunications goals d. meeting cost goals c. meeting corrmunications goals 6. 6 . ___ is the application of knowledge, skills, tools and techniques to project activities to meet project requirements. a. Project management b. Program management c. Project portfolio management d. Requirements management a. Project management 7. 7. Project portfolio management addresses ___ goals of an organization, while project management addresses ___ goa • . a. strategic, tactical b. tactical, strategic c....

Words: 4586 - Pages: 19

Premium Essay

Software Proposal

...18/3/2016 Table of Contents 1. Project Overview 3 1.1 Introduction and Scope management 4 1.1.2 Project Introduction 5 1.1.3 Project scope 6 1.2 Project organization 6 1.3 Management Subplan 7 1.3.1 Objectives and priorities 7 1.3.2 Assumptions 7 1.3.3 Dependencies 7 1.3.4 Constraints 7 1.4 Risk management plan 8 1.4.1 Handling the Project Emergency 9 1.4.2 Risk management process 10 1.4.3 Risk Management Organizational Responsibilities 11 1.5 Controlling and monitoring mechanisms 12 1.5.2 Communication plan 12 1.5.2 Communication plan 12 1.5.3 Staffing plan 12 1.5.4 Budget 12 2 Technical subplan 13 2.1 PBS 13 2.2 WBS 14 2.3 Network chart 14 3 Project summary 15 1 Project Overview This part of the “ OneFit ” Proposal provides an introduction of the purpose, scope, organization and objectives of the project for which the Plan has been written, the project assumptions , dependencies and constraints, a list of project deliverables, a summary of the project schedule and budget, a discussion of the risks and the plan for evolving the “ OneFit ” monitor system. 1.1 Introduction and Scope management 1.2.1 Project Introduction Project name is “ OneFit ”, and it is a monitor system, which can connected with different kinds of “OneFit” trackers and helping people to record their healthy data, e.g. Heart Rate, Sleeping Rate, Steps of the day, the frequency of doing exercise, etc. 1.2.2 Project Scope There are the main steps...

Words: 2430 - Pages: 10

Premium Essay

None

...with a different ELT member. The results of a new prioritization process—a list of IT projects that would be funded in 2004—had been unveiled only a few days earlier. But already a storm was gathering. The phone calls from other executives had common themes. All the callers had expressed concern that high priorities for their areas of the company had not been funded. Some had repeated views expressed during the prioritization process by people who worked for them about supposed categorization mistakes that penalized their business units. And each of the calls had concluded with an informal request to insert an unfunded project (or two) into the IT department’s work plans. “We don’t have to reopen the process,” the most recent caller had said, “but perhaps spare capacity might be applied to make some progress on this project in 2004—we’ve done this before, and it would mean a lot to our area and to the company’s growth plans.” The 10 business units that made up VWoA had proposed more than 40 projects, with funding requirements totaling $210 million (US). A budget of only $60 million (an amount capped by VWAG, the parent company of VWoA) made some degree of disappointment inevitable. But the intensity of pushback against the new process was surprising. The ELT had endorsed the idea of improving upon the old way these decisions were made, via unstructured debate among executive sponsors. The new process,...

Words: 6893 - Pages: 28

Premium Essay

Control Mangagment

...SDSU GE/OM 569 Project Management 3 April 2013 Where are we now? PMBOK – 5th Edition (2013) 1 Executing, Monitoring & Controlling Executing Process group consists of those processes performed to complete the work defined in the project management plan to satisfy the project specifications. Results may require planning updates & rebaselining Large portion of budget is expended performing the execution process group    3 Executing, Monitoring & Controlling… The Monitoring & Controlling process group consists of those processes required to track, review & orchestrate the progress & performance of the project, identifying any areas in which changes to the plan are required and initiate the corresponding changes. What work does it monitor & control?     Product work Project work 4 2 Executing, Monitoring & Controlling 5 Executing, Monitoring & Controlling 6 3 The Project is Up and Running: Now What? You want what? When! I have jury duty! The software doesn’t do that? That is not what I want! We have to be done by….! The software (critical) will be late! Why not add this?! You never asked for that?!? Just have your team do it! 7 Validate Scope 8 4 Validate Scope Validate Scope is the process of formalizing acceptance of the completed project deliverables. It includes…   Reviewing deliverables with the customer or sponsor to ensure they are completed satisfactorily, and Obtaining their...

Words: 5806 - Pages: 24

Premium Essay

Pm Skills

...1. 1. Approximately what percentage of the wortd's gross domestic product is spent on projects? a. 10 percent b. 25 percent c. 50 percent d. 75 percent b. 25 percent 2. 2. Which ofthe following is a I'IOt a potential advantage of using good projectmanagement?a. Shorter developmenttimesb. Higher workermoralec. Lower cost of capitald. Higher profitmargins c. Lower cost of capital 3. 3. A ___ is a temporary endeavor undertaken to create a unique product, service, or result. a . program b process c. project d . portfolio c. project 4. 4. Which of the following is not an attribute of a project? a. projects are unique b. projects are developed using progressive elaboration c. projects have a primary customer or sponsor d. projects involve little uncertainty d. projects involve little uncertainty 5. 5. Which of the following is not part of the triple constraint of project management? a. meeting scope goals b. meeting time goals c. meeting corrmunications goals d. meeting cost goals c. meeting corrmunications goals 6. 6 . ___ is the application of knowledge, skills, tools and techniques to project activities to meet project requirements. a. Project management b. Program management c. Project portfolio management d. Requirements management a. Project management 7. 7. Project portfolio management addresses ___ goals of an organization, while project management addresses ___ goa • . a. strategic, tactical b. tactical, strategic c....

Words: 4586 - Pages: 19

Premium Essay

Pmp Library

...Table of Contents Project Management................................................................3 Project Management Professional (PMP)®............................3 Diversity and Employment Compliance..............................13 ADA Compliance in Business...............................................13 Project Management Overview............................................3 Managing Projects within Organizations.............................3 Project Management .............................................................. Process Groups.....................................................................3 Execution, Monitoring and Controlling...............................3 Project Change Control and Closure...................................4 Initiation Basics, Developing a Project Charter and Project Management Plan...................4 Collecting Requirements and Defining Scope......................4 Monitor and Control Project Scope......................................4 Defining and Sequencing Project Activities..........................5 Developing and Controlling the Project Schedule...............5 Estimating Activity Resources and Durations......................5 Controlling Costs..................................................................5 Estimating & Budgeting Project Costs.................................6 Project Quality Planning......................................................6 Quality Assurance and Cost Control........

Words: 10262 - Pages: 42

Premium Essay

Assignment

...INX COLOUR BOOK PROJECT Eslsca 10 May 2015 Group (4) Shereif Gawish; Khaled Mousa; Mostafa Gamal; Marwa Said; Nevein Mahmoud; Basem Abdalla; Sherif Saad; Gamal Abd Elatif; Colour Book Project: 2   What is color book ? It is a book containing all colors made by INX applied on aluminum substrate sorted according to color categories 3 1. Introduction: Ali ElKattan 1.1. Project Description and Vision 4     Rexam is a beverage can making company where it stands as the 2nd biggest company in the industry of can making in the whole world. INX company is a pioneer company in the ink industry where it’s the main supplier for inks for Rexam & other companies. The company Vision is to grow through strategic partnerships, organic growth, and product innovation and to keep its aggressive market share. The project idea is to have and create a “Colour Book or Catalogue” where it is a book containing all colours applied on aluminium substrate sorted according to colour categories. Why ?? 5     The Project idea came because of the high spoilage of Ink & Cans & the long time for customer approval cycle was an important action point to Rexam & INX where the process almost took from 20 to 30 days where at this cycle processes INX & Rexam kept back & fourth with the customer for the colour satisfaction on the can colour. In addition to every time the customer refuses a sample almost 15,000 cans where...

Words: 1784 - Pages: 8