Free Essay

Cellphone Simulation

In:

Submitted By Dmandrew
Words 2331
Pages 10
Table of Contents Consensus versus Average Forecasting 1 Options 1 Demand Forecast 1 Supplier Selection 2 Change Orders 3 Lessons 3 Appendix A: Simulation Comments 4 Appendix B: Simulation Results 6

Consensus versus Average Forecasting
The consensus forecasts worked well for quick insight into estimated demand for each month. In our first year we used the consensus demand because we did not know the dynamics of the group, and we were relying on their expertise to guide us toward a more accurate forecast. As we progressed through the simulation we came to the realization that the consensus forecasts were often much different than the average estimated demand. After we analyzed the results of the first couple years, we noticed that the average demand was generally more accurate. This led us to the conclusion that the dynamics of the forecasting team were likely distorting the estimates for the consensus number. There were strong personalities within the team that seemed to sway the opinion of the team members to agree with them, thus lowering the accuracy of the estimation.
For the final two years we spent more time looking at the individual opinions of the team and tried to exclude estimates that were exceedingly high or low compared to the rest of the team. This gave us a number that was close to the average estimate of the team and allowed us to make a more accurate forecast. Overall, the consensus forecast was a good tool to use to quickly see whether demand was expected to be high or low. The biggest downside is the lack of accuracy. The average demand was a more accurate tool as long as we took the time to check each individual opinion to see how the number was made up. Our most successful forecasts seemed to come out of a combination of both the consensus and average.
Options
In general we tried to look at the overall benefits the option would provide. First we looked at the effect the option had on the consensus demand forecast. If the demand forecast went up, we decided to add the option to the phone because we believed we would be able to sell more units. The second deciding factor was whether or not the option increased profit for the model. We decided to add any option that would increase profit for the model. If the option increased both profit and consensus demand, we checked the graphs to look at the standard deviation. We avoided options that had a high standard deviation because we believed that there was more risk that the estimate would be inaccurate. A lower standard deviation indicated a higher level of confidence with the effect the option would have on demand. In retrospect we relied fairly heavily on the consensus estimates to choose the options. We realize that the consensus demand estimates were often inaccurate, and could have led us to choose options that were not beneficial to the models we were trying to sell. Just as we switched to using average demand estimates for our forecasting, we should have switched to using individual estimates when we were choosing options. It would have provided a greater level of accuracy and could have helped us make better decisions.
Demand Forecast
Initially we were reluctant to order too much stock because we were focused on the high cost of inventory becoming obsolete. This led to us experience a number of stock outs in our first year. We realized that this was costing us a substantial amount in lost profits. Due to this we changed our strategy for the following years to focus on ensuring we had products available to sell. Example of this would be in the first year, where we found the inventory cost of $4 per month and markdown loss was $17 per unit, but the profits were $70 for Model A and $90 for Model B. Using this as an example and a lesson learned from first year, we concluded that it would beneficial to carry excess inventories to compensate for fluctuations in demand, and that it is better to have more inventory and have the holding costs, than give up potential revenue for not having enough revenue . Carrying more inventories allowed us to sell more products and did not increase our holding costs to the point where profit was negatively impacted. Even with our change in strategy we still struggled with stock outs due to unanticipated fluctuations in demand. We were continuously conscious of the high costs of obsolete inventory and tried to avoid them by carrying just enough inventory to have a minimal amount left over, but we usually ended up with significant stock outs or a large amount of left over product.
In Retrospect if we were to run the simulation again we would focus on establishing that we had enough product to meet capacity. The lost profit due to selling out was incrementally high compared to the holding costs and obsolete costs, and if our inventories got to higher may have issued a change order, to try and finish will relatively low stock at the year instead of being reluctant to order much stock like we did in the first year. Also, we would have invested more in the marketing analysis; we found throughout the simulation that obtaining, as much information about demand is a very strong factor that will influence the accuracy of demand estimates as well as performance.
Supplier Selection
In the first year we avoided the suppliers with the higher set up costs and opted for suppliers with longer lead times and less capacity. We believed that these suppliers would provide us with some cost savings while still being able to meet our conservative demand estimate needs. We decided to allocate only on the basis of capacity, giving the supplier with the highest capacity to the model that was expected to sell more units. The supplier with the smaller capacity abilities was given to the model with less expected demand. During the simulation of the first year we realized that we were having serious flexibility issues with both demand and lead time. The supplier that had larger capacity had a lead time of four months and were producing well over what we had anticipated. By the time we realized we were over ordering stock, it was too late to make changes that would be profitable. Our second supplier with smaller capacity had great flexibility on time, but when we realized we needed much more stock to make greater profits, we found that the supplier was unable to meet these needs.
In the second year we knew we had to address these issues with flexibility in order to become more profitable. We decided to use the supplier with the longer lead time and greater capacity to provide both models with some level of stock that we knew would be in demand. That way we would not be forced to make any changes to the order from this supplier. We chose our second supplier based on the shorter lead time so that we could make quick changes when we experienced fluctuations in demand. This supplier was used to provide any additional stock that the first supplier did not cover. The flexibility in lead time allowed us to cut orders or add orders based on their capacity. As we were using suppliers with cheaper set up costs, we were still occasionally running into capacity constraints. In the third and fourth year we decided to switch our local supplier to one that could meet greater capacity demands. This allowed us greater flexibility in order changes which proved to be valuable. In retrospect we should have considered more than capacity in the first year. We discounted the necessity of flexibility in a market where demand is very unpredictable. In the future we would put higher priority on flexibility in order to capitalize on fluctuations in demand.

Change Orders
When the decision came up to make a change order, we first looked at the capacity capabilities of our suppliers to determine if they could meet the needs of a new order. If they could not meet capacity to a level that would offset the 2 million dollar cost to change the order, we did not change the order. If the supplier had the capacity capabilities or if we were trying to reduce our order, we then looked at the lead time of the supplier. Since our base inventory supplier had a lead time of four months, we decided that it would take too long to see the effects of a change order to offset the cost of sending a change order request. If we felt it was necessary to change our order with them, we knew it had to be as early in the year as possible to see the most benefit. However, we were still reluctant to make changes with them. Our local supplier had no lead-time so they were very effective at meeting our new requests. Also, if our local supplier was at full capacity, we never chose to implement a change order to our global supplier due to the long lead-time. We gave priority to addressing stock outs opposed to having too much inventory. As we stated before, we found that stocking out was more costly than holding too much inventory. We also found that it was much easier to place a request for a reorder when we had invested in market analysis. With a market analysis we were more certain of the demand, which made it possible to calculate the benefit of requesting a change order, and there was less risk of requesting a change order when it was not necessary.
Lessons
There were distinguishable lessons to take away from this simulation. Firstly, we learned that it is important to take the time to understand team dynamics when estimating demand. Different personalities can negatively impact the accuracy of a consensus forecast. It is necessary to look at all the information provided to gain a big picture understanding of differing opinions. This simulation also provided critical insight into how difficult forecasting can be in particular markets. We learned that it is not always a good idea to rely solely on a demand forecast to select suppliers. It is a good idea to select suppliers that will be able to accommodate changes in demand as information becomes available. Stemming from this, we learned that supplier flexibility within an unpredictable market is one of the most important factors. The right mix of capacity and lead times are critical to be able to match supply with demand.
The responsiveness of suppliers was a key aspect to meeting new demand levels, as long as the supplier also had the correct capacity capabilities. This was critical to highlighting the need to select multiple suppliers in order to gain benefits from both capacity and responsiveness. It also demonstrated that the whole process is inter-connected, starting with demand forecasts. If the forecasts are not accurate, then the options might not reflect the consumer preferences accurately. The suppliers and production numbers that have been chosen will be inaccurate and this may result in high inventory cost, obsolescence costs, and change order costs.

Appendix A: Simulation Comments
Year One
Design Room

The consensus demand will increase by 2K with the options we selected which seemed to be the highest of all the possible combinations of all the options. There is no impact on the profitability of either model without decreasing the consensus demand.

Forecasting Room

With no previous experience in demand forecasting we trusted our team to come up with a reliable consensus number, as they are trained professionals within the industry. As this is the first year of production we expect to learn from the results and adjust our estimates for the coming years. We have documented the estimates of each team member for analysis in the upcoming years.

Production Room

* Couldn’t access comments from simulation for this section*

Year Two
Design Room

We chose this combination of options because it increased the consensus demand forecast by 1K and also increased profits per model by $3. We feel that this is the best design.

Forecasting Room

We removed the outliers in the data to try and come up with a more stable average demand. Based on our results with the removal of the outliers the demand for Model A should be 50.4, and Model B should be 28.75. From this we rounded our estimates to the nearest number with a factor of 5.

Production Room

* Couldn’t access comments from simulation for this section*

Year Three
Design Room

We removed the outliers in the data to try and come up with a more stable average demand. Based on our results with the removal of the outliers the demand for Model A should be 50.4, and Model B should be 28.75. From this we rounded our estimates to the nearest number with a factor of 5.

Forecasting Room

The board seemed to be optimistic about demand and confident about their forecasts. We were a little hesitant to share their optimism due to previous years so we chose conservative numbers. We decided to chose numbers that more closely reflected the average demand estimates opposed to the consensus.

Production Room

* Couldn’t access comments from simulation for this section*

Year Four
Design Room

The speaker’s option gives an increase in demand and profit. It does not seem to have much deviation. It was the only option to increase both consensus demand and average demand.

Forecasting Room

We think this will be a good year for our models. We considered Joe to be lowballing the demand estimate because we decided to exclude the feature he wanted in the Model. Because of this we excluded his estimate from the data we used to make our decision

Production Room

* Couldn’t access comments from simulation for this section*

Appendix B: Simulation Results

Similar Documents

Premium Essay

Everest Executive Summary

...This report provides an in-depth analysis of the two Everest Simulations conducted by Group 10 of MGMT1001 Thursday Tutorial. This task required students to form teams consisting of five to six members whose goals were to summit Mount Everest. While it provided us with a rich experience in team dynamics and collaboration, it also enabled us to explore key managerial concepts taught in the course, consisting of: • Communication • Groups and Teams • Leadership In this report, we examine the effectiveness of Face to Face Communication (FTFC) versus Computer Mediated Communication (CMC), and the problems encountered through the utilisation of the virtual medium including efficiency of the feedback system, loss of personal focus and other emergent issues. It includes personal reflections on attitudes and perceptions, as well as group performance and strategies adopted in the second Simulation in order to create a more positive team experience. Theories which relate to interpersonal communication have also been integrated in the report to illustrate its relation to certain situations encountered during the Simulation. Additionally, we provide a multifaceted analysis on the notion of team cohesiveness and how it attributes to better performance outcomes. An overview on the different intragroup conflicts encountered in the Simulation has been included, examining the positive and negative impact that conflict had on team experience and performance, and how mutual agreements were reached...

Words: 287 - Pages: 2

Free Essay

Pom 333

...is a computer necessary in conducting a realworld simulation? Answer It is important because there are many different types of outcomes that comes in with simulation. Computers are used in daily life activities and it is necessary. 14-11 What is operational gaming? What is systems simulation? Give examples of how each may be applied. Answer Operational gaming is the use of simulation in competitive situations such as military games and business or management. System simulation ls that deal with the dynamics of large organizational or governmental systems. Validation The process of comparing a model to the real system that it represents to make sure that it is accurate. 14-17 (a) Resimulate the number of stockouts incurred over a 20-week period (assuming Higgins maintains a constant supply of 8 heaters). (b) Conduct this 20-week simulation two more times and compare your answers with those in part (a). Did they change significantly? Why or why not? (c) What is the new expected number of sales per week? Answer A. The number of stockouts incurred over a 20 week period is HOT WATER NUMBER OF HEATER SALES WEEKS THIS PER WEEK NUMBER WAS SOLD 3 2 4 9 5 10 6 15 7 25 8 12 9 12 10 10 B, Two more times would give us the value of a multiplied by 2. c. 25 14-18 A. 15 days of barge uploadings and average number of barges delayed B, They both are probabilistic simulations. Chapter 5 HW 5-14 Using MAD, determine whether...

Words: 648 - Pages: 3

Premium Essay

Student

...A SYSTEM SIMULATION STUDY ON THE THREE FAST MOVING PRODUCTS (MARLBORO, C2, VIVA) OF THE COLLEGE VARIETY SHOPPE USING THE MONTE CARLO SIMULATION IN INVENTORY MANAGEMENT EXECUTIVE SUMMARY This study shows how the selected three fast moving products (Marlboro cigarettes, C2, Viva mineral water) move from the current Inventory Management technique of the College Variety Shoppe from its distributors to its warehouse storage to the end user or customer. An excel program and a simulation model was made to observed its current performance. After the observation, the group performs an experimentation that will improve the current technique of the College Variety Shoppe. After simulating the experimentation, the group then give conclusions and recommendations on how to improve the College Variety Shoppe’s current Inventory Management. TABLE OF CONTENTS Title Page ........................................................ 1 Executive Summary ........................................................ 2 Table of Contents ........................................................ 3 Introduction ........................................................ 4 Methodology ........................................................ 6 Model Development ........................................................ 7 Model Validation ........................................................ 11 Experimentation, Results .......

Words: 2096 - Pages: 9

Premium Essay

Littlefield Simulation Report

...Initial operations strategy Prior to the commencement of the simulation, we examined the 50 days of historical data to glean as much information as we could about the operations. We performed some analysis in Excel and created a dashboard to illustrate various data. Specifically, we regressed the prior 50 days of jobs accepted to forecast demand over the next 2 - 3 months within a 95% confidence interval. The yellow and grey lines represent the maximum and minimum variability, respectively, based on two standard deviations (95%). Exhibit 1: Forecasted and actual demand by Day 50 and Day 270 Our two primary goals at the beginning of the simulation were as follows: 1) Eliminate bottlenecks and increase capacity in order to meet forecasted demand 2) Decrease lead time to 0.25 days in order to satisfy Contract 2 and maximize revenue In order to achieve these goals, we would need to know the capacity and throughput time of the entire system. We used the time required by each machine to process a lot to calculate capacity per station and then capacity of the entire production line (380 kits/day or 6 orders/day). In Exhibit 2 we can observe that the capacity of the production line is given by the station that produces the least number of units per day. Exhibit 2: Capacity of the production line The Decisions We decided to work with the maximum variability of demand because there was a penalty for late jobs and because there was no revenue for orders that took more than “x”...

Words: 765 - Pages: 4

Premium Essay

Monte Carlo Analysis

...Monte Carlo Statistical Analysis Name Course Instructor Date The Monte Carlo method is a mathematical method used for problem solving through the generation of random numbers and then observing a fraction of these numbers and the properties they obey. It is useful in obtaining numerical solutions to problems that are too complicated for analytical solutions. It is a form of probability used to understand the impact of risk and uncertainty in various areas such as financial and cost forecasting. It involves computation of the likelihood of given events occurring or not occurring, without taking into account the interaction of the elements involved in influencing the occurrence. The mathematical method was invented by Stanislaw Ulam in 1946 and named by Nicholas Metropolis after a classy gambling resort in Monaco, where a relative of Ulam frequently gambled [ (Fishman, 1996) ]. Concepts of the Monte Carlo method Uncertainty Being a forecasting model, there are assumptions that need to be made due to the uncertainty of various factors. One therefore needs to be able to make estimations of the expected results as they cannot predict with certainty what the end value will be. Important factors such as historical data and past experiences in the field can be helpful in making an accurate estimate. Estimation In some cases, estimation may be possible but in others it is not. In situations where estimation is possible, it is wise to use a wide range of possible values instead...

Words: 2486 - Pages: 10

Free Essay

Advances in Metal Forming Research at the Center for Precision Forming

...materials such as Ultra/Advanced High Strength Steels (U/AHSS), aluminum alloys, magnesium alloys and boron steels in automotive industry is increasing to reduce vehicle weight and increase crash performance. The use of these relatively new materials requires advanced and reliable techniques to a) obtain data on material properties and flow stress, b) predicting springback and fracture in bending and flanging, c) selecting lubricants and die materials/coatings for stamping and forging and d) designing tools for blanking and shearing. In addition, designing the process and tooling for a) hot stamping of boron steels, b) warm forming of Al and Mg alloys, and c) optimizing the use of servo-drive presses require advanced Finite Element based simulation methods. CPF is conducting R&D in most of these topics and also in many hot and cold forging related topics. This paper gives an overview of this research and discusses how the research results are applied in cooperation with industry. Keywords: Metal Forming, Sheet metal, Forging, FEM 1 INTRODUCTION The Center for Precision Forming (CPF) has been established with funding from the National Science Foundation (NSF) and a number of companies (www.cpforming.org). CPF is an outgrowth of the Engineering Research Center for Net Shape Manufacturing (ERC/NSM – www.ercnsm.org) and conducts research in sheet metal forming while ERC/NSM focuses on cold and hot forging related R&D projects. Both Centers work closely with industry under contract....

Words: 3894 - Pages: 16

Free Essay

Comp 125

...Introduction This chapter describes our work in evolution of buildable designs using miniature plastic bricks as modular components. Lego 1 bricks are well known for their flexibility when it comes to creating low cost, handy designs of vehicles and structures. Their simple modular concept make toy bricks a good ground for doing evolution of computer simulated structures which can be built and deployed. Instead of incorporating an expert system of engineering knowledge into the program, which would result in more familiar structures, we combined an evolutionary algorithm with a model of the physical reality and a purely utilitarian fitness function, providing measures of feasibility and functionality. Our algorithms integrate a model of the physical properties of Lego structures with an evolutionary process that freely combines bricks of different shape and size into structures that are evaluated by how well they perform a desired function. The evolutionary process runs in an environment that has not been unnecessarily constrained by our own preconceptions on how to solve the problem. The results are encouraging. The evolved structures have a surprisingly alien look: they are not based in common knowledge on how to build with brick toys; instead, the computer found ways of its own through the evolutionary search process. We were able to assemble the final designs manually and confirm that they accomplish the objectives introduced with our fitness functions. This chapter...

Words: 438 - Pages: 2

Free Essay

Ims of Tcs in Pakistan

...developed, operated and maintained the Concept Simulator since 1998. The Concept Simulator models the functional operation and inter-operation of key components of train control system architecture and the external systems to which the system interfaces. The simulator is valuable in the development and analysis of operational principles, and in assessing design trade-offs. The SEA-designed facility simulates operation at ERTMS Levels 1, 2, and 3. Components include a Communications Network, a Network Management Centre, a generic Interlocking, a Radio Block Centre, a Track Simulator including both conventional and TCS equipment, a Driver Desk, a European Vital Computer and a Driver MMI. The components are modelled using software-based simulations hosted on networked PCs. The simulator has been valuable in the engineering evaluation and validation of emergent system architectures, and enables system constraints to be explored and defined. ERTMS operational modes and the transitions between them are simulated and ERTMS principles and procedures are followed. Innovative Customer Information System (ICIS) SEA's Innovative Customer Information System (ICIS) is capable of managing and displaying customer information, including real time information, in a visually dynamic manner. The system utilises intelligent screens and wireless technology to distribute data, thus minimising installation and commissioning efforts. The system will be suitable for any transport environment, mobile...

Words: 397 - Pages: 2

Free Essay

Simulation Modeling

...Brooklyn Warren Chapter 10 Simulation Modeling What is Simulation? * To try to duplicate the features, appearance, and characteristics of a real system. * Imitate a real-world situation mathematically. * Study its properties and operating characteristics. * Draw conclusions and make action decisions based on the results. Processes of Simulation: 1. Define Problem 2. Introduce Important Variables 3. Construct Simulation Model 4. Specify Values of Variables to Be Tested 5. Conduct the Simulation 6. Examine the Results 7. Select Best Course of Action Advantages of Simulation: * Straightforward and flexible. * Can handle large and complex systems. * Allows "what-if" questions. * Does not interfere with real-world systems. * Study interactions among variable. * "Time comparison" is possible. * Handles complications that other methods can't. Disadvantages of Simulation: * Can be expensive and time consuming. * Does not generate optimal solutions. * Managers must generate all conditions and constraints. * Each model is unique. Monte Carlo Simulation: Can be used with variables that are probabilistic. Steps: * Establish the probability distribution for each random variable. * Use random numbers to generate random values. * Repeat for some number of replications. Probability Distributions: Historical data Goodness-of-fit tests for common distributions: ...

Words: 259 - Pages: 2

Premium Essay

Mat 540

...678-679 of the text. Using simulation estimate the loss of revenue due to copier breakdown for one year, as follows: 1. In Excel, use a suitable method for generating the number of days needed to repair the copier, when it is out of service, according to the discrete distribution shown. 2. In Excel, use a suitable method for simulating the interval between successive breakdowns, according to the continuous distribution shown. 3. In Excel, use a suitable method for simulating the lost revenue for each day the copier is out of service. 4. Put all of this together to simulate the lost revenue due to copier breakdowns over 1 year to answer the question asked in the case study. 5. In a word processing program, write a brief description/explanation of how you implemented each component of the model. Write 1-2 paragraphs for each component of the model (days-to-repair; interval between breakdowns; lost revenue; putting it together). 6. Answer the question posed in the case study. How confident are you that this answer is a good one? What are the limits of the study? Write at least one paragraph. There are two deliverables for this Case Problem, the Excel spreadsheet and the written description/explanation. Please submit both of them electronically via the dropbox. The assignment will be graded using the associated rubric. |Outcome Assessed: |Create statistical analysis of simulation results. ...

Words: 673 - Pages: 3

Premium Essay

Jet Copy

...Jet Copy Simulation Prepared by Joe Miller Prepared for February 7th 2013 TABLE OF CONTENTS INTRODUCTION SUMMARY JET COPY SIMILATION CONCLUSION AND RECOMMENDATIONS APPENDIX INTRODUCTION The purpose of this report is to examine the feasibility to for Jet Copy to purchase a second copy machine. Based on copies produced and lost with only the use of one copier. In this report I will use data from a simulation to assist in the determination of an additional copier for Jet Copy. As a reminder that this is a random simulation and the information in the simulation will only assist between when the test stop and 52 week will not have great affect on the outcome of the in the decision making. The simulation that was run was base on a 52 week scenario. The actual results are based on 51 week trial. The difference between the 51 week test and the actual 52 weeks will not have any great impact on the recommendation. ------------------------------------------------- SUMMARY This report creates a simulation that shows one possible outcome for Jet Copier when there one copier is out for repair for up to 4 days. It will also aid in the decision to ad d or not to add a second copier. This report will answer the following questions: 1. Using Excel to generate the number of days needed to repair the copier. 2. Using Excel to generate the interval between successive breakdowns according to continuous distribution. 3. Using Excel, use a suitable method to...

Words: 968 - Pages: 4

Free Essay

How to Write

...Class: Seminar in Organizational Theory & Behavior Professor :Dr. Dyck's Bio Name: Zhihui Dai Change Management Simulation: Power and Influence Abstract Within this program Change Management Simulation: Power and Influence, I am a Director Product Innovation manager in Spectrum Sunglass Company, which is a private company that designs, manufactures, and sells sunglasses. What I need do is convince people adapt my proposal. I should choose method from 18 change levers that attempt to convince workers to adapt my new proposal that will change their attitude from awareness, interest, trial, to adoption. I must decide the proper method and use the time wisely. Be able to increase credibility and achieve the greatest percentage of adopters. Key words: Convince percentage of adoption credibility limited time This Management Simulation Project from Harvard provides students a virtual experience to convince people in start-up companies. When I started the first test run of the simulation there are various decisions, However, if an administrator make the wrong move, then I lose credibility and set the proposal is a backwards. On the other hand, if I decide on a correct decision, then not only will I get the workers are more interested in my proposal, but it also increases the credibility of the workers. When I was implementing change behavior, building a coalition of support is a important tool to get satisfied from people. When I simulate this behavior, I can have more...

Words: 942 - Pages: 4

Free Essay

Using a Combined Method of Hierarchical Analysis and Monte Carlo Simulation in Order to Identify and Prioritize the Target Market Selection Criteria

...Applied mathematics in Engineering, Management and Technology 2 (2) 2014:466-475 www.amiemt-journal.com Using a combined method of hierarchical analysis and Monte Carlo simulation in order to identify and prioritize the target market selection criteria (Case study: Food distribution companies of Mashhad-Iran) Amir kariznoee Ph.D. student of Industrial Management,University of Mazandaran ,Iran (Corresponding Author's E-mail: Amir.kariznoee@yahoo.com) Monireh Bijandi Graduate of Accounting in Ferdowsi University of Mashhad,Iran Mahdi Ghayur Maddah Student of Public Management in Ferdowsi University of Mashhad,Iran Vajihe Mogharabi M.A. Student of Information Technology Management, Shahid beheshti University,Tehran,Iran Abstract The aim of this study is to identify and prioritize the key factors in selecting a target market in the food industry. In order to determine the components and subcomponents of this study, we have used previous researches in this area. In order to match these factors with the food industry situation and create a hierarchical structure, we have obtained the opinions of 323 experts about affecting factors on choosing a market in this industry with the use of questionnaire. Then, using a combination of hierarchal analysis process and Monte Carlo simulation and cooperation with 10 senior executives of distribution companies, the weight of each component and sub-component was determined. In general, four components and ten sub-components were...

Words: 3589 - Pages: 15

Free Essay

Simulation

...INTRODUCTION: The purpose of this paper is to bring out the use of Simulation by Managers of various organizations. Under discussion will be:  Definition of simulation.  Model construction.  When and why it becomes handy to use simulation.  Steps used in simulation technique.  Random selection in simulation.  Advantages / benefits derived from use of simulation technique.  Disadvantages /Challenges associated with simulation technique.  Role of computer in simulation.  Conclusion / comments. Definition of simulation: Simulation can be defined as a quantitative technique which describes a process by developing a model of that process and then conduct a series of organized trial and error experiments to predict the behavior of the process through time often with the aid of a computer. It is a method that is used to solve a problem in many areas of management, for example inventory management, queuing problems, profit analysis and project management among others. Model construction: A successful simulation model has to be carefully designed in order to achieve the intended predictive purpose. Therefore important factors have to be considered such as; i. It must be objective oriented. It must be constructed for a purpose and be able to achieve that purpose. ii. Critical variables and relationships. These must be identified and incorporated in model. However it is not essential or indeed desirable to include all variables in the model. iii. Simplicity...

Words: 1498 - Pages: 6

Free Essay

Baudrillard Response

...What is a simulacrum (the singular form of simulacra)?  Please explain the examples Baudrillard musters to support his "explanation" of simulacra.  What factors or forces have made our age (the postmodern era) an age of simulacra?  What benefits and risks does this postmodern, hyperreal age present? When Baudrillard refers to “simulacra,” Baudrillard is talking about simulating, as stated in the text, simulation threatens the difference between “true” and “false,” between “real” and “imaginary”. The examples Baudrillard uses to explain this word is when the text relates to being ill. “A person can go to bed and make believe he is ill. But someone who simulates an illness produces in himself some of the symptoms.” A big source Baudrillard relates to is religion. The belief in a God is considered simulacra, there are many beliefs of different gods and different way of presenting the different gods but which ones are true and which are false. There is not any true way of proving which Gods are true, therefore it becomes a simulacrum. This also plays a role in today’s day in age; there are still many different religions and beliefs that are still believed in. Watergate is a key example when looking at simulaca, as a few people made something look real but at the same time was also fake. and stated in the text, to simulate is to feign to have what one hasn’t. One Implies a presence, the other an absence. But the matter is more complicated, since to simulate is not simply...

Words: 259 - Pages: 2