Free Essay

Cost Overruns

In:

Submitted By deliciabrice72
Words 724
Pages 3
Cost Overruns
Delicia Brice
PM3320
Professor Johnson
September 16, 2014 Abstract
Project management is to forecast and track costs to avoid cost overruns. Poor management leads to rising cost. Effective project management identifies such possible sources of cost overruns early and mitigates their effect. This paper explains the underlying causes of project cost overruns and provides some cost estimating methods used to avoid the overruns in the project.
Cost Overruns
Cost can be described as one of the most important issues of a project success. A cost overrun is the amount by which the actual cost exceeds the budgeted, estimated, original, or target cost. Society sees cost overruns as the norm. They are a built-in part of most projects despite the much acquired knowledge in project management. The most common reason for this are listed below. Low initial cost estimates are often the result of underestimating bids for subcontracts or the actual costs come in, they are often higher than anticipated. Such cost overruns are due either to incorrect estimates or to changed conditions in the marketplace. With a budget number in mind, you can start to assess the cost range of the project you have in mind with a Ballpark estimate. An overall review may find that increases in some areas are compensated by decreases in others. You may be able to adjust requirements to reduce costs or seek out lower-cost suppliers. Advising the business owners or managers of possible higher costs at this stage gives them the option of making changes and maintaining their budgets.
Unanticipated technical difficulties are the root of poor design. Sometimes, the designs or drawings that form the basis of the project are not realistic. You may find that a combination of specified features is difficult to achieve or that drawings show an incorrect arrangement. Executing the project as specified will either cost extra or cause problems that must be resolved later at additional cost. Using the feasibility estimate, the project manager has to continuously compare plans with executed work to find such discrepancies early and correct them.
Specifications changes often voids the initial cost estimates. The project progresses according to a plan that assigns durations to project tasks. The Sponsor makes small changes in the plan that necessitates other changes which lead to still more changes ... and so on. Because estimates are predictions of future costs, there is always the potential for error, and cost overruns are more the norm than the exception. Consequently, additional allowances are needed to act as a buffer, so that the funds actually allocated to the project will be sufficient. This allowance is known as contingency
Lack of Scope leads to the creation of projects that have no clear purpose. Changes in the scope of supply within a project frequently cause cost overruns. These changes result from new requirements that the owners introduce and fixes for functions that don't work as specified. As project manager, you must confirm a comprehensive project plan is in place; all activities and their sequence required for project completion have been identified, and all major purchase orders have been submitted based on known prices and availabilities of materials and equipment. Given that definitive estimates are developed further down the project life cycle with more accurate information and fewer project uncertainties, these estimates provide a much more accurate expected cost of the project at completion, with a ±5 percent margin of error.
External factors such as unexpected rising store prices, environmental factors could lead to cost escalation. While building something you required material & labor. When the inflation occur the price of the items & services increase, day to day essential things like food, fuel, consumer goods are become costly, thus this also effect individual & company. Therefore the material price or manufactured things are become costly as the raw material prices goes up and similarly services are also become costlier. As a project manager you want the cost estimates to be as accurate as possible. Bottom-up estimating decomposes the work into more detail which is aggregated into the total project cost. The accuracy depends on the size of the project and the complexity of the work but this method is considered the most accurate technique

Reference
Hotchkiss, L. (2014). Research Methods and Society: Foundations of Social Inquiry Upper Saddle River, New Jersey: Pearson.

Similar Documents

Free Essay

Is4550 Unit 3 Assignment 1

...any Mom & Pop store. Unfortunately, when your weakest link is your security policy frameworks you put yourselves in a position of unnecessary risk. We are tasked in this assignment to list things that can affect your business if your company’s framework doesn’t align with the business. Without further adieu here are those results. The first subject that was discussed was operations. Operations focus on various manual processes while ensuring there is minimal risk of errors. For example, if your company is still using paper-based ledgers for your daily paperwork and accounting. You would want to switch your systems to some sort of business software. Overall this will save you both time and money. You also must be careful not to all cost overrun. If your business is not streamlined you can definitely run the risk of this. Risk mitigation is the process of reducing risks as close to the point of absolute zero as possible. Using non-standardized methodologies, and non-compliance with regulatory requirements can damage your company beyond the point of no return. This is because, in the case of non-standardized methodologies, you will be using different processes in different departments and expecting those departments to be able to interact smoothly. Non-compliance with regulatory requirements can subject your business to fees which can easily cripple your business or destroy it outright. When discussing performance, it is all about speed. Using faster equipment, faster business...

Words: 378 - Pages: 2

Premium Essay

Jk Cement

...University of San Carlos School of Business and Economics Department of Business Administration In Partial Fulfillment with the Requirements for BA111A: Strategic Management JK Cement Submitted by: BACUS, Xaviera Faye DELA PAZ, Niña Christine GARCIA, Angelou LANGOMEZ, Stephanie PLASENCIA, Riza Mae Submitted to: Sir Angelo Oledan Burdeos February 2016 HISTORY/BACKGROUND OF THE COMPANY: .K.Cement started its commercial production in May 1975 in its first plant Nimbahera in Rajasthan. The company was incorporated in the year 1994. Today J. K. Cement is one of the largest cement manufacturers in north India. It is also second largest producer of white cement in India. The company exports white cement to countries like South Africa, Nigeria, Singapore, Bahrain, Bangladesh, Sri Lanka, Tanzania, UAE and Nepal. The company has two manufacturing facilities located at Nimbahera and Mangrol in the state of Rajasthan. The company produces white cement and its production unit is located in Gotan at Rajasthan. STATEMENT OF THE PROBLEM: What must be the decision of Dr. Ancheta about the “unusual” expansion of JK Cement in order to increase their productions to supply the projected demands? AREAS OF CONSIDERATIONS: 1. The Company JK Cement started operations in 1968. It is located very near Metro Manila where the demand for cement is most concentrated. JK Cement makes use of the domestic market and 15 percent of Metro Manila market. 2. Internal and External...

Words: 756 - Pages: 4

Premium Essay

Cmgt 410

...Project Controls CMGT 410 ANALYSIS AND REPORTING OF UNPLANNED CHANGES: If any unexpected modifications occur, in the training assignment, regardless of whether before or during the training session, will need to be informed instantly to the stakeholders concerned, administrators, and CEO, for authorization. This will be a compulsory measure, before any other will be taken. Unexpected modifications will always be that which are unpredicted. Some of these might include modifications which exceed budget limitations initially included in the estimations. One of the methods we are going to avoid cost overruns will be to provide passes to the students. The passes will have affixed lanyards and they should be put on all the time. This will prevent rivals from showing to the occasion, getting information for our training, and offering a cost overrun. EVALUATION OF THE PROJECT QUALITY: For being the project administrator, I will be deciding the best methods to follow. Within these kinds of methods, I will pick which limitations will be most important, and which will be least important, in order to concentrate our financial resources in the best possible way. If I do encounter any kind of problems, I'll use the best judgment in arriving at my judgments, accounting for the best plan of action, with the minimum amount of financial effect. The scope will always be considered the main objective of the assignment, with financial effect of every decision being close at mind. The assignment...

Words: 700 - Pages: 3

Free Essay

Case Study

...basic business letter format. Type the recipient’s address at the top left of the page. Skip a line and type the date. Start the letter with Dear Mr., Ms. or Mrs., unless you are very well acquainted with the recipient. Skip a line between each paragraph and close the letter with “Sincerely” followed by your name and title. Make Your Point Use the opening paragraph to briefly explain the purpose of the letter. Your first sentence might read, “A recent review of construction purchase orders revealed several cost overruns,” or “We would like to offer you a 15 percent discount on your next printing job.” State the purpose clearly and avoid jargon or highly technical language. If a secretary or assistant reads the recipient’s mail, you’ll want to make sure that person understands the significance of your letter, even if she doesn’t have a technical background. Details, Details, Details Expand upon the first paragraph with more details. You might mention that cost overruns occurred during construction of the building’s elevator shafts or note that the 15 percent discount applies to printing jobs costing more than $100. Short, concise letters might be more likely to be read, but make sure you provide enough details so that the recipient fully understands the reason for the letter. Keep in mind that the tone of your letter can affect the way the reader perceives it. The Purdue Online Writing Lab suggests using positive words as much as possible and focusing on what your company can...

Words: 762 - Pages: 4

Premium Essay

Junk Case Study

...1. Who do you believe is at fault in this situation? I believe that the Project Manager is at fault in this situation. The structures manager strongly advised the project manager not to stop the activities in this department before testing the plant’s high-pressure pneumatic and electrical systems. The structures manager warned the project manager and even mentioned that the test was scheduled for the next month. I think it would have been more important to consider this risk and prevent this from happening, alone from a safety perspective. The project manager also mentioned that his boss expects him to finish this project without a cost overrun. However, maybe it would have been of importance to run this particular issue by his boss in order to either increase the budget or adjust the scope in order to successfully and safely finish the project. 2. Should the structures manager have been dedicated enough to continue to work on his own? Why or Why not? This was running through my head for a little while after I read the text. It’s difficult to say. However, the structures manager did try to convince the project manager that it was a big risk to take and the project manager went ahead and took the risk. Even though the structures manager knew that this could potentially happen, the project manager did not listen to his advice. If he would have continued to work on his own, he would have disobeyed, he could have prevented the plant from exploding, however...

Words: 325 - Pages: 2

Premium Essay

Supply Chain Management

...| BDFG | 24.9 | ACDFG | 28.7 | BEG | 15.7 | Grant Chart 3.15 ABEF: 6 weeks ACF: 7 weeks The critical path is ACF Activity | Time | ES | EF | LS | LF | Slack | Critical | A | 1 | 0 | 1 | 0 | 1 | 0 | YES | B | 1 | 1 | 2 | 2 | 3 | 1 | NO | C | 4 | 1 | 5 | 1 | 5 | 0 | YES | E | 2 | 2 | 4 | 3 | 5 | 1 | NO | F | 2 | 5 | 7 | 5 | 5 | 0 | YES | 3.18 We have: AD (11 weeks), B (8 weeks), CE (12 weeks). So CE is the critical path Activity | Daily Crash Cost | Maximum Crash | A | 100 | 1 day | B | 50 | 2 days | C | 100 | 1 day | D | 150 | 2 days | E | 200 | 3 days | So if Crash C by 1 day ($ 100) to 11 days Crash C by 1 day ($200) and A by 1 day ($100) to 10 days Crash E by 2 days ($400) and D by 2 days ($300) to 8 days Totally, the minimum cost of crashing by 4 days is: $100 + $200 +$100+$400+$300 = $1,100 2. Find a recent or historical news story about a major mismanaged project and discuss the problems that had faced such as cost overruns, delays or under-performance. With the purpose of improving safety and correcting operational problems incurred as a result of the traffic queues formed by slow moving vehicles and a curve with an operational speed of 20 miles-per-hour, the SB I-405 freeway is created as one of useful method. The I-405 Sepulveda Pass...

Words: 1402 - Pages: 6

Free Essay

Panama Canal Expansion Project: Have American Fears Come True?

...four years ago, when Panama awarded the lucrative contract to expand its inter-oceanic canal to a mostly European consortium, the United States was not pleased. An American company whose bid was unsuccessful, Bechtel, thought the winning tender would barely pay for pouring the concrete and that the consortium would probably try to renegotiate the price at some stage during the construction process. Some might argue that those American doubts have been justified, especially in view of the ongoing economic row between the European consortium and the Panamanian government agency that runs the waterway. The spat has threatened to bring work to a grinding halt, unless the two parties manage to resolve a $1.6bn (£1bn) dispute over cost overruns. A series of WikiLeaks cables from the US embassy in Panama that were revealed by the Spanish daily newspaper El Pais in 2010 provided an inside view of the frustration that was felt in the US at not having been able to get that contract. Bechtel had been strongly backed by the US embassy, which was fully aware that the deal would have meant millions of dollars' worth of business for US suppliers. US ports expanding Instead, the contract was secured by the GUPC consortium (co-led by Spanish company Sacyr and Italian Impregilo), which had offered considerably less money than other bidders but whose proposal, in the opinion of the canal authority, had the best...

Words: 794 - Pages: 4

Premium Essay

Implmentation Process

...Making Changes Making some changes in the response plan is to be expected. If problems exist, then you should address them promptly. There are two routes to making changes, which depend on the nature of the problems that are experienced–replanning and redesigning: •Replanning is the most common form of change resulting from a response. This will result from problems such as time delays, cost overruns, and system blockages. They require immediate decisions to be made to "tweak" the system to get the implementation back on track. They require you to revisit the original plan and work out how to make modifications to ensure the response is completed as expected. Indeed, this will be part of the normal process of response implementation, in which monitoring identifies problems you must address, which in turn results in replanning of the response so that implementation can continue. •Redesigning involves more fundamental changes, but is far less common than replanning. This may be necessary if it becomes clear that a planned response is simply unworkable, or where there are negative outcomes that far outweigh the likely positive achievements. Under these circumstances, it may be necessary to halt the response implementation and return to the drawing board, selecting alternative interventions that might be more feasible⁄effective. This should not be viewed as a negative process. Indeed, it is more acceptable to accept that the response is not working and start the process again...

Words: 259 - Pages: 2

Free Essay

Unit 3 Assignment 1: Security Policy Frameworks

...for any company from Apple to Microsoft to any Mom & Pop store. Unfortunately, when your weakest link is your security policy frameworks you put yourselves in a position of unnecessary risk. We are tasked in this assignment to list things that can affect your business if your company’s framework doesn’t align with the business. The first subject that was discussed was operations. Operations focus on various manual processes while ensuring there is minimal risk of errors. For example, if your company is still using paper-based ledgers for your daily paperwork and accounting. You would want to switch your systems to some sort of business software. Overall this will save you both time and money. You also must be careful not to all cost overrun. If your business is not streamlined you can definitely run the risk of this. Risk mitigation is the process of reducing risks as close to the point of absolute zero as possible. Using non-standardized methodologies, and non-compliance with regulatory requirements can damage your company beyond the point of no return. This is because, in the case of non-standardized methodologies, you will be using different processes in different departments and expecting those departments to be able to interact smoothly. Non-compliance with regulatory requirements can subject your business to fees which can easily cripple your business or destroy it outright. When discussing performance, it is all about speed. Using faster equipment, faster business...

Words: 322 - Pages: 2

Free Essay

Mba Student

...Government of India Ministry of Finance Department of Economic Affairs Public Private Partnership Projects in India Compendium of Case Studies c Government of India Ministry of Finance Department of Economic Affairs Public Private Partnership Projects in India Compendium of Case Studies December 2010 Public Private Partnership projects in India Compendium of Case Studies © Department of Economic Affairs All rights reserved Published by: PPP Cell, Department of Economic Affairs Ministry of Finance, Government of India New Delhi-110 001, India www.pppinindia.com Disclaimer This Compendium of Case Studies has been prepared as a part of a PPP capacity building programme that is being developed by the Department of Economic Affairs, Ministry of Finance, Government of India (DEA) with funding support from the World Bank, AusAID South Asia Region Infrastructure for Growth Initiative and the Public Private Infrastructure Advisory Facility (PPIAF). A consulting consortium, consisting of Economic Consulting Associates Limited (ECA) and CRISIL Risk and Infrastructure Solutions Limited (CRIS), commissioned by the World Bank, has prepared this compendium based on extensive external consultations. ECA and CRIS have taken due care and caution in preparing the contents of this compendium. The accuracy, adequacy or completeness of any information contained in this toolkit is not guaranteed and DEA,World Bank, AusAID, PPIAF, ECA or CRIS are not responsible...

Words: 73739 - Pages: 295

Free Essay

Tufs

...INVESTIGATING TUFS There are number of problems that can be addressed from this case. The two main issues I noticed in this case is lack of communication and lack of interest shown by the underwriting managers. TUFS (Technical Underwriting Financial Systems) was a project that was going to help Northern Insurance transform their underwriting process and also provide strategic business capabilities. As, per the case there was a lot of excitement when the project begun two years ago but it looks like as the time passed by the focus from the project shifted as the interest kept getting lower from the all the team that were involved. Hence the project was completed on time and in budget but the TUFS system has turned into a nightmare in its first few months of operation and was not delivering what it was built for i.e. to streamline and transform their underwriting process. Looking at the problem I think the issue started at a very early phase of the project where requirements for the project were not well-defined. Also as this project was the most highly invested project in IT interest and attention was required by the CIO and CFO all along the project. It seemed like the CIO Martin Drysdale who was in charge of this major project didn’t take that responsibility to track the project and keep everyone on their feet while completing the requirements that were needed for this project to be a success. Being in charge of a huge project that is going to effect the whole organization you...

Words: 1141 - Pages: 5

Premium Essay

Paper

...below budget by $27,081 but exceeded last year by $42,992.. There were a lot of groups in house with meetings scheduled at different Hotels. There was six comp events that only got food & beverage credits only. Due to these events Payroll was high over by 18k cost for these events were 17k. Director salary was not in the budget. Cleaning supplies & laundry came in high due to comp events also in a contract with Aramark ($1,300 a week) contract was not budgeted. Tavern 17 fell below budget by $22,433 due to groups in house that had dinners off property from city wide. Another contributing factor was breakfast coupons recorded at $9.0 versus a full value of $20.95. Tavern average check was $12.92 that exceeded budget by $1.21 driven by up selling and pricing. Coffee Bar had a good month but finished under budget by $36. Coffee Bar average check $4.99 exceeded the budget by $.41. Displayed cases are revamped and new items are added. Room Service performed well and exceeded budget by $2,968. Room Service check average 14.00 exceeded the budget by $.98, this is was a result of our volume focused strategy. Food Cost finished at 24.3% compared to a budget of 25.% exceeding budget due to very good controls in place.. Beverage Cost finished at 25.9% on a budget of 25.3. Total Food and Beverage Revenues ended below budget by $27.0K but exceeded last year by $42.9K. Revenue shortfall was mainly in Tavern 17 by $22.2K, followed by Banquets $8.0K. Although Food and Beverage revenue...

Words: 561 - Pages: 3

Premium Essay

Fasttac Essay

...FOR IMMEDIATE RELEASE: 08.23.17 FASTTAC, Inc. Awarded the GSA Schedule ___________________ Fasttac, a tech company specializing in new construction technology, has been awarded the GSA Schedule. Fasttac CEO Ray Steeb believes this development will allow the company to reach more construction managers and architects looking for a better way to conduct maintenance management programs. According to Steeb, “Fasttac is pleased to make our product available through GSA.” The company’s products are aimed to increase the level of efficiency in the facility management and facility maintenance industry. “Making the purchase procurement process simpler for our prospective government clients,” says Steeb, “will help their facilities reach greater efficiency faster.” Using a patented navigation system and specialized software, Fasttac allows users to organize facility and/or construction information in a way that makes it accessible. The company holds several patents that record and produce institutional knowledge faster than any other product in the construction software market. Since 2006, Fasttac has been providing facilities with a solution for managing and organizing 2D construction drawings in a 3D grid. Fasttac’s navigation system makes it possible to move between trade drawings digitally. Construction drawings and other facility information can be viewed and recorded at any location, allowing any user to have access when they need it, where they need it. Their extensive software...

Words: 547 - Pages: 3

Free Essay

Chaos Report

...Chaos Report The Standish Group is a widely known source of independent primary research and analysis of IT project performance. In 1995, the Standish Group published the CHAOS Report, an often-quoted analysis that focuses on the failure of IT projects to better improve overall IT project performance. The CHAOS Report had documented monetary loss on software developments for unsuccessful projects. The Standish Group comprised such data using focus groups, in depth surveys and executive interviews discussing project performance of completed IT projects. The CHAOS Report provides data on the failure rate of IT projects and also details common explanations for such failure. The authors of the CHAOS Report describe the advantageous process of building bridges to accentuate the lack thereof in software development; Alfred Spector had used such a comparison originally in his article, a computer science perspective of bridge design. The concept is that an error, which resulted in the collapse in a bridge, can be so great in its severity that investigations were subsequently done, allowing those involved in the building process to learn from their mistakes. Differentially, the computer industry allegedly covers up, ignores and/or rationalizes the errors or shortcomings that led up to the failure. The Standish Group contends that project failures will decrease if the following is focused on following a project failure: the scope of software project failure, main factors that cause...

Words: 1523 - Pages: 7

Free Essay

Acc 350 Wk 7 Quiz 5 Chapter 6 - All Possible Questions

...ACC 350 WK 7 Quiz 5 Chapter 6 - All Possible Questions To Purchase Click Link Below: http://strtutorials.com/ACC-350-WK-8-Quiz-6-Chapter-7-All-Possible-Questions-ACC3507.htm ACC 350 WK 8 Quiz 6 Chapter 7 - All Possible Questions 1) The master budget is one type of flexible budget. 2) A flexible budget is calculated at the start of the budget period. 3) Information regarding the causes of variances is provided when the master budget is compared with actual results. 4) A variance is the difference between the actual cost for the current and previous year. 5) A favorable variance results when budgeted revenues exceed actual revenues. 6) Management by exception is the practice of concentrating on areas not operating as anticipated (such as a cost overrun) and placing less attention on areas operating as anticipated. 7) The essence of variance analysis is to capture a departure from what was expected. 8) A favorable variance should be ignored by management. 9) An unfavorable variance may be due to poor planning rather than due to inefficiency. 10) The only difference between the static budget and flexible budget is that the static budget is prepared using planned output. 11) The static-budget variance can be subdivided into the flexible-budget variance and the sales-volume variance. 12) The flexible-budget variance may be the result of inaccurate forecasting of...

Words: 457 - Pages: 2