Proj 586 (Project Management) Final Exam Answers

In: Other Topics

Submitted By MaryMartinson
Words 15761
Pages 64
PROJ 586 (Project Management) Final Exam Answers http://hwguiders.com/downloads/proj-586-project-management-final-exam-answers/ 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. (Points : 5) 2. (TCO H) What is the longest phase of the project life cycle? (Points : 5) 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. (Points : 5) 4. (TCO D) All of the following are risk response types except _____. (Points : 5)
5. (TCO F) The two most common types of project reports are _____. (Points : 5) 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. (Points : 5) 7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5) 8. (TCO A) Projects are identified and selected in the _____. (Points : 5)
9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? (Points : 5) 10. (TCO F) The budget for each work package is _____. (Points : 5) 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. (Points : 5) 12. (TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days. (Points : 5) Bottom of Form
Page 2
1. (TCO B) Describe the benefits of including the people who will be involved in performing the project when planning the project. (Points : 10)
2. (TCO E)
Part 1: Discuss some types of conflict that might arise during a project. (15 points)
Part 2: Describe two examples that have these types of…...

Similar Documents

Proj 420 (Project Risk Management) Final Exam Answers

...PROJ 420 (Project Risk Management) Final Exam Answers To Buy this Class Copy & paste below link in your Brower http://homeworklance.com/downloads/proj-420-project-risk-management-final-exam-answers/ Or Visit Our Website Visit : http://homeworklance.com Email Us : lancehomework@gmail.com PROJ 420 (Project Risk Management) Final Exam Answers (TCO 1) Project risk has its origins in (Points : 5) (TCO 2) The identification process produces (Points : 5) (TCO 3) The outputs of the identification step include (Points : 5) (TCO 4) Risk assessment involves two basic functions: (Points : 5) . (TCO 5) Secondary risk is caused by (Points : 5) (TCO 6) The reporting step is designed to fulfill the function of (Points : 5) (TCO 7) Minor risk reviews can occur (Points : 5) (TCO 8) Requested changes to the risk plan should be submitted through the (Points : 5) (TCO 1) Structured project risk management is (Points : 5) (TCO 2) Once we identify the risks, we look to see if (Points : 5) (TCO 3) A standard risk checklist includes (Points : 5) (TCO 4) The first document produced at the end of the Assessment step is (Points : 5) (TCO 5) The key to carrying out the implementation plan is (Points : 5) (TCO 6) The risk interview will (Points : 5 (TCO 7) The implementation plan actions include (Points : 5) (TCO 8) One of the reasons a post-project review is not done is (Points : 5) (TCO 1) If we do not manage risk we will......

Words: 6796 - Pages: 28

Proj 586 (Project Management) Final Exam Answers

...PROJ 586 (Project Management) Final Exam Answers Follow Link Below To Get Tutorial https://homeworklance.com/downloads/proj-586-project-management-final-exam-answers/ Description: 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. (Points : 5) 2. (TCO H) What is the longest phase of the project life cycle? (Points : 5) 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. (Points : 5) 4. (TCO D) All of the following are risk response types except _____. (Points : 5) 5. (TCO F) The two most common types of project reports are _____. (Points : 5) 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. (Points : 5) 7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5) 8. (TCO A) Projects are identified and selected in the _____. (Points : 5) 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? (Points : 5) 10. (TCO F) The budget for each work package is _____. (Points : 5) 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. (Points : 5) 12. (TCO C)......

Words: 993 - Pages: 4

Proj 586 (Project Management) Final Exam Answers

...PROJ 586 (Project Management) Final Exam Answers Follow Link Below To Get Tutorial https://homeworklance.com/downloads/proj-586-project-management-final-exam-answers/ Description: 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. (Points : 5) 2. (TCO H) What is the longest phase of the project life cycle? (Points : 5) 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. (Points : 5) 4. (TCO D) All of the following are risk response types except _____. (Points : 5) 5. (TCO F) The two most common types of project reports are _____. (Points : 5) 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. (Points : 5) 7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5) 8. (TCO A) Projects are identified and selected in the _____. (Points : 5) 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? (Points : 5) 10. (TCO F) The budget for each work package is _____. (Points : 5) 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. (Points : 5) 12. (TCO C)......

Words: 2977 - Pages: 12

Proj 586 (Project Management) Final Exam Answers

...PROJ 586 (Project Management) Final Exam Answers Follow Link Below To Get Tutorial https://homeworklance.com/downloads/proj-586-project-management-final-exam-answers/ Description: 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. (Points : 5) 2. (TCO H) What is the longest phase of the project life cycle? (Points : 5) 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. (Points : 5) 4. (TCO D) All of the following are risk response types except _____. (Points : 5) 5. (TCO F) The two most common types of project reports are _____. (Points : 5) 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. (Points : 5) 7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5) 8. (TCO A) Projects are identified and selected in the _____. (Points : 5) 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? (Points : 5) 10. (TCO F) The budget for each work package is _____. (Points : 5) 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. (Points : 5) 12. (TCO C)......

Words: 6945 - Pages: 28

Proj-586 Project Management Final Exam Solution

...PROJ-586 Project Management Final Exam Solution http://uphomework.com/downloads/proj-586-project-management-final-exam-solution/ 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. (Points : 5) 2. (TCO H) What is the longest phase of the project life cycle? (Points : 5) 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. (Points : 5) 4. (TCO D) All of the following are risk response types except _____. (Points : 5) 5. (TCO F) The two most common types of project reports are _____. (Points : 5) 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. (Points : 5) 7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5) 8. (TCO A) Projects are identified and selected in the _____. (Points : 5) 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? (Points : 5) 10. (TCO F) The budget for each work package is _____. (Points : 5) 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. (Points : 5) 12. (TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3......

Words: 986 - Pages: 4

Proj 586 (Project Management) Final Exam Answers

...PROJ 586 (Project Management) Final Exam Answers http://hwguiders.com/downloads/proj-586-project-management-final-exam-answers/ 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. (Points : 5) 2. (TCO H) What is the longest phase of the project life cycle? (Points : 5) 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. (Points : 5) 4. (TCO D) All of the following are risk response types except _____. (Points : 5) 5. (TCO F) The two most common types of project reports are _____. (Points : 5) 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. (Points : 5) 7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5) 8. (TCO A) Projects are identified and selected in the _____. (Points : 5) 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? (Points : 5) 10. (TCO F) The budget for each work package is _____. (Points : 5) 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. (Points : 5) 12. (TCO C) Calculate the earliest start for Task B if its predecessor, Task......

Words: 15761 - Pages: 64

Proj 586 (Project Management) Final Exam Answers

...PROJ 586 (Project Management) Final Exam Answers Follow Link Below To Get Tutorial https://homeworklance.com/downloads/proj-586-project-management-final-exam-answers/ Description: 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. (Points : 5) 2. (TCO H) What is the longest phase of the project life cycle? (Points : 5) 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. (Points : 5) 4. (TCO D) All of the following are risk response types except _____. (Points : 5) 5. (TCO F) The two most common types of project reports are _____. (Points : 5) 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. (Points : 5) 7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5) 8. (TCO A) Projects are identified and selected in the _____. (Points : 5) 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? (Points : 5) 10. (TCO F) The budget for each work package is _____. (Points : 5) 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. (Points : 5) 12. (TCO C)......

Words: 3969 - Pages: 16

Proj 586 (Project Management) Final Exam Answers

...PROJ 586 (Project Management) Final Exam Answers Follow Link Below To Get Tutorial https://homeworklance.com/downloads/proj-586-project-management-final-exam-answers/ Description: 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. (Points : 5) 2. (TCO H) What is the longest phase of the project life cycle? (Points : 5) 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. (Points : 5) 4. (TCO D) All of the following are risk response types except _____. (Points : 5) 5. (TCO F) The two most common types of project reports are _____. (Points : 5) 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. (Points : 5) 7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5) 8. (TCO A) Projects are identified and selected in the _____. (Points : 5) 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? (Points : 5) 10. (TCO F) The budget for each work package is _____. (Points : 5) 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. (Points : 5) 12. (TCO C)......

Words: 993 - Pages: 4

Proj-586 Project Management Final Exam Answers

...PROJ-586 Project Management Final Exam Answers http://www.projbid.com/downloads/proj-586-project-management-final-exam-answers/ 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. (Points : 5) 2. (TCO H) What is the longest phase of the project life cycle? (Points : 5) 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. (Points : 5) 4. (TCO D) All of the following are risk response types except _____. (Points : 5) 5. (TCO F) The two most common types of project reports are _____. (Points : 5) 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. (Points : 5) 7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5) 8. (TCO A) Projects are identified and selected in the _____. (Points : 5) 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? (Points : 5) 10. (TCO F) The budget for each work package is _____. (Points : 5) 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. (Points : 5) 12. (TCO C) Calculate the earliest start for Task B if its predecessor,......

Words: 987 - Pages: 4

Proj 586 Final Exam Answers

...PROJ 586 Final Exam Answers https://hwguiders.com/downloads/proj-586-final-exam-answers PROJ 586 Final Exam Answers 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. 2. (TCO H) What is the longest phase of the project life cycle? 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. 4. (TCO D) All of the following are risk response types except _____. 5. (TCO F) The two most common types of project reports are _____. 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. 7. (TCO G) Which of the following is not an advantage of using project management software? 8. (TCO A) Projects are identified and selected in the _____. 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? 10. (TCO F) The budget for each work package is _____. 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. 12. (TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days. 13. (TCO B) Describe the benefits of including the people who will be involved......

Words: 922 - Pages: 4

Proj 586 Final Exam Answers

...PROJ 586 Final Exam Answers http://www.homeworkwarehouse.com/downloads/proj-586-final-exam-answers/ PROJ 586 Final Exam Answers SET # 1 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. 2. (TCO H) What is the longest phase of the project life cycle? 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. 4. (TCO D) All of the following are risk response types except _____. 5. (TCO F) The two most common types of project reports are _____. 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. 7. (TCO G) Which of the following is not an advantage of using project management software? 8. (TCO A) Projects are identified and selected in the _____. 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? 10. (TCO F) The budget for each work package is _____. 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. 12. (TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days. SET # 2 1. (TCO B) Describe the benefits of including the people who will be involved......

Words: 927 - Pages: 4

Proj 586 Final Exam Answers

...PROJ 586 Final Exam Answers https://hwguiders.com/downloads/proj-586-final-exam-answers PROJ 586 Final Exam Answers 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. 2. (TCO H) What is the longest phase of the project life cycle? 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. 4. (TCO D) All of the following are risk response types except _____. 5. (TCO F) The two most common types of project reports are _____. 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. 7. (TCO G) Which of the following is not an advantage of using project management software? 8. (TCO A) Projects are identified and selected in the _____. 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? 10. (TCO F) The budget for each work package is _____. 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. 12. (TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days. 13. (TCO B) Describe the benefits of including the people who will be involved......

Words: 922 - Pages: 4

Proj 586 (Project Management) Final Exam Answers

...PROJ 586 (Project Management) Final Exam Answers Follow Link Below To Get Tutorial https://homeworklance.com/downloads/proj-586-project-management-final-exam-answers/ Description: 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. (Points : 5) 2. (TCO H) What is the longest phase of the project life cycle? (Points : 5) 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. (Points : 5) 4. (TCO D) All of the following are risk response types except _____. (Points : 5) 5. (TCO F) The two most common types of project reports are _____. (Points : 5) 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. (Points : 5) 7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5) 8. (TCO A) Projects are identified and selected in the _____. (Points : 5) 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? (Points : 5) 10. (TCO F) The budget for each work package is _____. (Points : 5) 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. (Points : 5) 12. (TCO C)......

Words: 993 - Pages: 4

Proj 586 (Project Management) Final Exam Answers

...PROJ 586 (Project Management) Final Exam Answers Follow Link Below To Get Tutorial https://homeworklance.com/downloads/proj-586-project-management-final-exam-answers/ Description: 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. (Points : 5) 2. (TCO H) What is the longest phase of the project life cycle? (Points : 5) 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. (Points : 5) 4. (TCO D) All of the following are risk response types except _____. (Points : 5) 5. (TCO F) The two most common types of project reports are _____. (Points : 5) 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. (Points : 5) 7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5) 8. (TCO A) Projects are identified and selected in the _____. (Points : 5) 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? (Points : 5) 10. (TCO F) The budget for each work package is _____. (Points : 5) 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. (Points : 5) 12. (TCO C)......

Words: 993 - Pages: 4

Proj 586 (Project Management) Final Exam Answers

...PROJ 586 (Project Management) Final Exam Answers Follow Link Below To Get Tutorial https://homeworklance.com/downloads/proj-586-project-management-final-exam-answers/ Description: 1. (TCO A) In a _____ organization, the project manager does not have complete authority over the project team. (Points : 5) 2. (TCO H) What is the longest phase of the project life cycle? (Points : 5) 3. (TCO B) A(n) _____ is defined as a piece of work that consumes time. (Points : 5) 4. (TCO D) All of the following are risk response types except _____. (Points : 5) 5. (TCO F) The two most common types of project reports are _____. (Points : 5) 6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time. (Points : 5) 7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5) 8. (TCO A) Projects are identified and selected in the _____. (Points : 5) 9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints? (Points : 5) 10. (TCO F) The budget for each work package is _____. (Points : 5) 11. (TCO F) The _____ for the entire project or for each work package provides a baseline against which actual cost and work performance can be compared at any time during the project. (Points : 5) 12. (TCO C)......

Words: 993 - Pages: 4