Question: What role does the Critical Path play in EV Analysis?
The Expert Says: In our example the positive schedule variance indicates the project is ahead of schedule. However, the critical path for this project is A – C – E and requires additional evaluation. Delays on the critical path will impact the end date and deserve special attention. Here task A is on the CP and is significantly (10%) behind schedule. Be careful when analyzing project totals for SV and SPI as the Critical Path is not directly taken into consideration!

The Expert Says
Question: Should the PM use slack at will?
The Expert Says: Slack is a great tool for the Project Manager to help manage the project schedule and complete the project on time. Slack is really "flexibility" in the schedule along the non-critical paths which can be utilized when required to compensate for unforeseen circumstances. Slack should be used with discretion because using slack will decrease the "flexibility" and move non-critical paths closer to becoming critical.

The Expert Says
Question: If we know how far we can crash all the tasks, why don't we just crash them at them all the way and avoid working the iterative process?
The Expert Says: Be careful not to shorten the tasks on the critical path too much, otherwise we may not be spending our money efficiently. In the diagram below, the "all crashed" line shows us by adding resources to all tasks, we can finish in 22 days instead of 29 days. By taking the iterative approach we have saved money by not crashing all tasks. By adding resources to tasks A and D, we can finish between 22 and 23 days. Adding resources to only task A would allow the project to be completed in 23 to 24 days. If we shorten only task G, 25 days; only task C, 26 to 27 days, and only task E, 28 days. Keep in mind the cost is increased when we crash each task to

Similar Documents

Premium Essay

Ops 571 Week 5 Project Management Proposal

...OPS 571 WEEK 5 PROJECT MANAGEMENT PROPOSAL A+ Graded Tutorial Available At: http://hwsoloutions.com/?product=ops-571-week-5-project-management-proposal Visit Our website: http://hwsoloutions.com/ Product Description OPS 571 Week 5 Project Management Proposal, Project Management Proposal Introduction The following proposal will describe a project proposal for Riordan Manufacturing process. Riordan is the leading industrialist of plastic products and has a customer base in the medical, automotive, aircraft, governmental, supply chain (suppliers to businesses that utilize bottles or appliances). The company has various locations in the United States and globally, with over 550 employees, and provides a range of products and services (University of Phoenix, 2013). Currently, Riordan manufacturing process is outdated and uncoordinated. Therefore, the purpose of the project plan to impose a strategic plan for data collection and reporting, exceed ISO 9000 standards, minimize costs, increase profit margin, and secure future innovations for continuous sustainability. Data Collection and Reporting The International Organization for Standardization (ISO) 9000 provides various aspects for quality management to help meet customer’s needs (International Organization for Standardization, 2014). The restructuring tactics should consider those set provisions as well as an internal order for daily operations. In addressing the listed goals, the project team should automate and...

Words: 818 - Pages: 4

Premium Essay

Week 1

...MGMT- 404 PROJECT MANAGEMENT STATEMENT OF PARTICIPation This document will contain the information needed for your team operations, guidelines and commitment. It should be kept in doc sharing and each update should have a version control identifier (e.g., Team A SOP v1, v2, v3, etc.). IMPORTANT NOTE: The statement of participation must be posted in the team’s doc sharing area and the final submission must be available for the team to review and approve each week. Approval can be achieved by downloading the document. If you have disagreements, it is critical to contact your project leader and get a correction posted immediately. The professor should be notified of any disagreements. If the statement of participation is not submitted, the entire team will receive the same grade (including any point loss from other team members). I. Team Information PROJECT NAME: | MEMBER NAME | # | PHONE # | | EMAIL | | MEETING AVAILABILITY | Jade Xiong | 1 | | | | | Monday at 5 / email/ phone | Raquel Godoy | 2 | | | | | Monday at 5/ email/ phone | Genaro Zavala | 3 | | | | | Monday at 5/ email /phone | | 4 | | | | | | | 5 | | | | | | | 6 | | | | | | II. Weekly meeting schedule The most successful teams schedule at least (2) meetings a week throughout the course. Scheduling standing meetings allows everyone to schedule this time in advance and coordinate other activities around the scheduled meeting times. Meetings can change...

Words: 1698 - Pages: 7

Premium Essay

Project Implementation, Control, and Termination Paper

...MGT/437 Version 4 Project Management | Copyright © 2009, 2006, 2004 by University of Phoenix. All rights reserved. Course Description This course examines project management roles and environments, the project life cycle, and various techniques of work planning, control, and evaluation for project success. Policies Faculty and students/learners will be held responsible for understanding and adhering to all policies contained within the following two documents: University policies: You must be logged into the student website to view this document. Instructor policies: This document is posted in the Course Materials forum. University policies are subject to change. Be sure to read the policies at the beginning of each class. Policies may be slightly different depending on the modality in which you attend class. If you have recently changed modalities, read the policies governing your current class modality. Course Materials Kerzner, H. (2006). Project management: A systems approach to planning, scheduling, and controlling (9th ed.). Hoboken, NJ: Wiley. Meredith, J. R. & Mantel, S. J. (2006). Project management: A managerial approach (6th ed.). Hoboken, NJ: Wiley. All electronic materials are available on the student website. Software Microsoft® Project® 2007 (Virtual Desktop) Week One: Project Definition | | Details | Due | Points | Objectives | 1.1 Determine the importance of project management in the current...

Words: 1839 - Pages: 8

Premium Essay

Bus 519 Week 1 Bus519 Week 1

... http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 BUS 519 Week 1 Discussion "What is Risk?"  Please respond to the following: * There are three (3) schools of thought regarding risk. The first considers the positive and negative aspects of risk, but sees them as separate. The second group believes that there are benefits from treating threats and opportunities together, while the third school does not label uncertainties, but addresses uncertainty as part of “doing the job.” Argue the value of having a risk strategy despite the cost associated with it. Include an example to support your response. Provide a rationale for your selection and determine how this approach helps a project to be successful. BUS 519 Week 2 Discussion "Need for Risk Management" Please respond to the following: * There are four (4) critical success factors that are important for effective risk management: supportive organization; competent people; appropriate methods, tools and techniques; and simple, scalable process. Determine three (3) obstacles for an organization to manage risk effectively. Suggest strategies from the perspective of a project manager to avoid the obstacles. BUS 519 Week 3 Discussion "Project Initiation" Please respond to the following: * Using the “Stakeholder Analysis Template” (Appendix B2 in the Hillson and Simon text) for a company that you currently work...

Words: 2421 - Pages: 10

Premium Essay

Bus 519 Week 5 Bus519 Week 5

...Answer: http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 BUS 519 Week 1 Discussion "What is Risk?"  Please respond to the following: * There are three (3) schools of thought regarding risk. The first considers the positive and negative aspects of risk, but sees them as separate. The second group believes that there are benefits from treating threats and opportunities together, while the third school does not label uncertainties, but addresses uncertainty as part of “doing the job.” Argue the value of having a risk strategy despite the cost associated with it. Include an example to support your response. Provide a rationale for your selection and determine how this approach helps a project to be successful. BUS 519 Week 2 Discussion "Need for Risk Management" Please respond to the following: * There are four (4) critical success factors that are important for effective risk management: supportive organization; competent people; appropriate methods, tools and techniques; and simple, scalable process. Determine three (3) obstacles for an organization to manage risk effectively. Suggest strategies from the perspective of a project manager to avoid the obstacles. BUS 519 Week 3 Discussion "Project Initiation" Please respond to the following: * Using the “Stakeholder Analysis Template” (Appendix B2 in the Hillson and Simon text) for a company that you currently work...

Words: 2422 - Pages: 10

Premium Essay

Bus 519 Week 11 Bus519 Week 11

...Answer: http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 BUS 519 Week 1 Discussion "What is Risk?"  Please respond to the following: * There are three (3) schools of thought regarding risk. The first considers the positive and negative aspects of risk, but sees them as separate. The second group believes that there are benefits from treating threats and opportunities together, while the third school does not label uncertainties, but addresses uncertainty as part of “doing the job.” Argue the value of having a risk strategy despite the cost associated with it. Include an example to support your response. Provide a rationale for your selection and determine how this approach helps a project to be successful. BUS 519 Week 2 Discussion "Need for Risk Management" Please respond to the following: * There are four (4) critical success factors that are important for effective risk management: supportive organization; competent people; appropriate methods, tools and techniques; and simple, scalable process. Determine three (3) obstacles for an organization to manage risk effectively. Suggest strategies from the perspective of a project manager to avoid the obstacles. BUS 519 Week 3 Discussion "Project Initiation" Please respond to the following: * Using the “Stakeholder Analysis Template” (Appendix B2 in the Hillson and Simon text) for a company that you currently work...

Words: 2422 - Pages: 10

Premium Essay

Project Management-for This Project, You May

...Project management-For this project, you may Click Link Below To Buy: http://hwcampus.com/shop/project-management-for-this-project-you-may/ Project management-For this project, you may For this project, you may choose one that is of interest to you, or you may choose to begin planning for your senior project. When selecting a project, avoid picking one that is either too big or too small. For example, do not decide to build a new stadium for your local sports team (too big) or to plant your summer garden (too small). Here are some successful past project ideas. • The opening of a coffee shop • A charity event for a local social service agency • A meditation pool and platform in the center of town • A redevelopment of a local playground • Design and installation of a computer network for a small business • Software development project A project to build a house or create a website is NOT acceptable. You are not limited to the list of projects above. Please refer all questions concerning what is acceptable as a class project to your instructor. Milestones: • Due Week 1: Project Outline Proposal/Approval • Due Week 2: Project Charter • Due Week 3: Scope Statement • Due Week 4: Work Breakdown Structure/Gantt Chart • Due Week 5: Risk Management Plan • Due Week 6: Project Schedule and Budget • Due Week 7: Communication Plan • Due Week 8: Final Project Package Week 1 Back to Top Due Week 1: Project Outline Proposal/Approval To begin Week 1, all...

Words: 1512 - Pages: 7

Premium Essay

No Title

...Project Management Plan Horace Bethea, Nicole Brown, Eric Cornick, Robin Evans, and Kristi Longstreet CPMGT/301 November 19, 2012 Steven Chardon-Strunk Project Management Plan Because of strict accreditation regulations and laws related to Title IV of the Higher Education Act of 1965 for institutions offering federal financial aid, an organization cannot offer traditional sales bonuses for employees who enroll students. Recently there has been a decline in employee morale. Senior management thinks that a new employee incentive program may boost employee morale (University of Phoenix, 2012, para. 3). This paper will include the work breakdown structure, activities, the sequenced activity diagram, a human resources plan, and a communication plan. The communication methods identified in the communication plan will be evaluated by identifying the communication tools and techniques most effective for the audience, and an explanation of why the methods of communication identified are most effective. The objective to this project management planning process is to successfully implement an employee incentive program within the university to boost employee morale that has declined because of the changes in compensation structure. Although the university cannot control what laws and regulations are changed governing federal financial aid, the university must abide by the changes to keep their accreditation. The university...

Words: 4553 - Pages: 19

Premium Essay

Intl Business

... |The Business School | | |Course Code/ID: |BSMAN 3005 | | |Course Title: |Project Management | | |Teaching Location: |(Insert Teaching Location) | | |Program(s): |Bachelor of Applied Management | | |Author: |Alan Labas | | |Level: |Advanced ...

Words: 3271 - Pages: 14

Premium Essay

Bus 519 Complete Course Bus519 Complete Course

... http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 BUS 519 Week 1 Discussion "What is Risk?"  Please respond to the following: * There are three (3) schools of thought regarding risk. The first considers the positive and negative aspects of risk, but sees them as separate. The second group believes that there are benefits from treating threats and opportunities together, while the third school does not label uncertainties, but addresses uncertainty as part of “doing the job.” Argue the value of having a risk strategy despite the cost associated with it. Include an example to support your response. Provide a rationale for your selection and determine how this approach helps a project to be successful. BUS 519 Week 2 Discussion "Need for Risk Management" Please respond to the following: * There are four (4) critical success factors that are important for effective risk management: supportive organization; competent people; appropriate methods, tools and techniques; and simple, scalable process. Determine three (3) obstacles for an organization to manage risk effectively. Suggest strategies from the perspective of a project manager to avoid the obstacles. BUS 519 Week 3 Discussion "Project Initiation" Please respond to the following: * Using the “Stakeholder Analysis Template” (Appendix B2 in the Hillson and Simon text) for a company that you currently work...

Words: 2421 - Pages: 10

Premium Essay

Bus 519 Week 4 Bus519 Week 4

...Answer: http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 BUS 519 Week 1 Discussion "What is Risk?"  Please respond to the following: * There are three (3) schools of thought regarding risk. The first considers the positive and negative aspects of risk, but sees them as separate. The second group believes that there are benefits from treating threats and opportunities together, while the third school does not label uncertainties, but addresses uncertainty as part of “doing the job.” Argue the value of having a risk strategy despite the cost associated with it. Include an example to support your response. Provide a rationale for your selection and determine how this approach helps a project to be successful. BUS 519 Week 2 Discussion "Need for Risk Management" Please respond to the following: * There are four (4) critical success factors that are important for effective risk management: supportive organization; competent people; appropriate methods, tools and techniques; and simple, scalable process. Determine three (3) obstacles for an organization to manage risk effectively. Suggest strategies from the perspective of a project manager to avoid the obstacles. BUS 519 Week 3 Discussion "Project Initiation" Please respond to the following: * Using the “Stakeholder Analysis Template” (Appendix B2 in the Hillson and Simon text) for a company that you currently work...

Words: 2422 - Pages: 10

Premium Essay

Bus 519 Week 7 Bus519 Week 7

...Answer: http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 BUS 519 Week 1 Discussion "What is Risk?"  Please respond to the following: * There are three (3) schools of thought regarding risk. The first considers the positive and negative aspects of risk, but sees them as separate. The second group believes that there are benefits from treating threats and opportunities together, while the third school does not label uncertainties, but addresses uncertainty as part of “doing the job.” Argue the value of having a risk strategy despite the cost associated with it. Include an example to support your response. Provide a rationale for your selection and determine how this approach helps a project to be successful. BUS 519 Week 2 Discussion "Need for Risk Management" Please respond to the following: * There are four (4) critical success factors that are important for effective risk management: supportive organization; competent people; appropriate methods, tools and techniques; and simple, scalable process. Determine three (3) obstacles for an organization to manage risk effectively. Suggest strategies from the perspective of a project manager to avoid the obstacles. BUS 519 Week 3 Discussion "Project Initiation" Please respond to the following: * Using the “Stakeholder Analysis Template” (Appendix B2 in the Hillson and Simon text) for a company that you currently work...

Words: 2422 - Pages: 10

Premium Essay

Bus 519 Week 8 Bus519 Week 8

...Answer: http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 BUS 519 Week 1 Discussion "What is Risk?"  Please respond to the following: * There are three (3) schools of thought regarding risk. The first considers the positive and negative aspects of risk, but sees them as separate. The second group believes that there are benefits from treating threats and opportunities together, while the third school does not label uncertainties, but addresses uncertainty as part of “doing the job.” Argue the value of having a risk strategy despite the cost associated with it. Include an example to support your response. Provide a rationale for your selection and determine how this approach helps a project to be successful. BUS 519 Week 2 Discussion "Need for Risk Management" Please respond to the following: * There are four (4) critical success factors that are important for effective risk management: supportive organization; competent people; appropriate methods, tools and techniques; and simple, scalable process. Determine three (3) obstacles for an organization to manage risk effectively. Suggest strategies from the perspective of a project manager to avoid the obstacles. BUS 519 Week 3 Discussion "Project Initiation" Please respond to the following: * Using the “Stakeholder Analysis Template” (Appendix B2 in the Hillson and Simon text) for a company that you currently work...

Words: 2422 - Pages: 10

Premium Essay

Bus 519 Week 2 Bus519 Week 2

... http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 BUS 519 Week 1 Discussion "What is Risk?"  Please respond to the following: * There are three (3) schools of thought regarding risk. The first considers the positive and negative aspects of risk, but sees them as separate. The second group believes that there are benefits from treating threats and opportunities together, while the third school does not label uncertainties, but addresses uncertainty as part of “doing the job.” Argue the value of having a risk strategy despite the cost associated with it. Include an example to support your response. Provide a rationale for your selection and determine how this approach helps a project to be successful. BUS 519 Week 2 Discussion "Need for Risk Management" Please respond to the following: * There are four (4) critical success factors that are important for effective risk management: supportive organization; competent people; appropriate methods, tools and techniques; and simple, scalable process. Determine three (3) obstacles for an organization to manage risk effectively. Suggest strategies from the perspective of a project manager to avoid the obstacles. BUS 519 Week 3 Discussion "Project Initiation" Please respond to the following: * Using the “Stakeholder Analysis Template” (Appendix B2 in the Hillson and Simon text) for a company that you currently work...

Words: 2421 - Pages: 10

Premium Essay

Bus 519 Week 9 Bus519 Week 9

...Answer: http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 http://workbank247.com/q/bus-519-complete-course-bus519-complete-course/22300 BUS 519 Week 1 Discussion "What is Risk?"  Please respond to the following: * There are three (3) schools of thought regarding risk. The first considers the positive and negative aspects of risk, but sees them as separate. The second group believes that there are benefits from treating threats and opportunities together, while the third school does not label uncertainties, but addresses uncertainty as part of “doing the job.” Argue the value of having a risk strategy despite the cost associated with it. Include an example to support your response. Provide a rationale for your selection and determine how this approach helps a project to be successful. BUS 519 Week 2 Discussion "Need for Risk Management" Please respond to the following: * There are four (4) critical success factors that are important for effective risk management: supportive organization; competent people; appropriate methods, tools and techniques; and simple, scalable process. Determine three (3) obstacles for an organization to manage risk effectively. Suggest strategies from the perspective of a project manager to avoid the obstacles. BUS 519 Week 3 Discussion "Project Initiation" Please respond to the following: * Using the “Stakeholder Analysis Template” (Appendix B2 in the Hillson and Simon text) for a company that you currently work...

Words: 2422 - Pages: 10