The following case represents a realistic situation facing construction firm that has just won a competitive contract. The realistic conditions complicating the project are described in detail, as are the alternatives offered by the staff for dealing with these complexities.

Case
The Sharon Construction Corporation

The Sharon Construction Corporation has been awarded a contract for the construction of a 20,000-seat stadium. The construction must start by February 15 and be completed within one year. A penalty clause of $15,000 per week of delay beyond February 15 of next year is written into the contract.
Jim Brown, the president of the company, called a planning meeting. In the meeting he expressed great satisfaction at obtaining the contract and revealed that the company could net as much as $300,000 on the project. He was confident that the project could be completed on time with an allowance made for the usual delays anticipated in such a large project.
Bonnie Green, the director of personnel, agreed that in a normal year only slight delays might develop due to a shortage of labor. However, she reminded the president that for such a large project, the company would have to use unionized employees and that the construction industry labor agreements were to expire on November 30. Past experience indicated a fifty-fifty chance of a strike. Jim Brown agreed that a strike might cause a problem. Unfortunately, there was no way to change the contract. He inquired about the prospective length of a strike. Bonnie figured that such a strike would last either eight weeks (70 percent chance) or possibly 12 weeks (30 percent chance). Jim was not pleased with these prospects. However, before he had a chance to discuss contingency plans he was interrupted by Jack White, the vice-president for engineering. Jack commented that a colder December that had been assumed...

Similar Documents

Premium Essay

The Sharon Construction

...ENGINEERING MANAGEMENT 1 ASSIGNMENT 2 - PROJECT SCHEDULING & CRASHING Please answer both questions (10% towards final subject marks) 1. The Sharon Construction Corporation The Sharon Construction Company has been awarded a contract for the construction of a 20,000-seat stadium. Construction works must start by February 15 and be completed within one year. A penalty clause of $15, 000 per week of delay beyond February 15 of next year is written into the contract. Jim Brown, the president of the company, called a planning meeting, where he expressed great satisfaction at obtaining the contract and revealed that the company could net as much as $300, 000 on the project. He was confident that the project could be finished on time with an allowance made for the usual delays anticipated in such a large project. Bonnie Green, the director of personnel, agreed that in a normal year only slight delays might develop due to a shortage of labor. However, she reminded the president that for such a large project, the company would have to use unionized employees and that the construction industry labor agreements were to expire on November 30. Past experience indicated a fifty-fifty chance of a strike. Jim Brown agreed that a strike might cause a problem. Unfortunately, there was no way to change the contract. He inquired about the prospective length of a strike. Bonnie figured that it would last either 8 weeks (70% Chance) or possibly 12 weeks (30% chance). Jim was not...

Words: 393 - Pages: 2

Premium Essay

The Sharon Construction Corporation

...The Sharon Construction Corporation The Sharon Construction Corporation has been awarded a contract for the construction of a 20,000 seat stadium. The construction must start by 28th February 2013 and be completed within one year. A penalty clause of $15,000 per week of delay beyond 28th February of 2014 is written in the contract. Jim Brown, the president of the company, called a planning meeting. In the meeting he expressed great satisfaction at obtaining the contract and revealed that the company could profit as much as $300,000 on this project. This total project will cost $2,000,000 according to the contact. He was confident that the project could be completed on time. Bonnie Green, the project manager, agreed that in a normal year only slight delays might develop due to shortage of labor. However, she reminded the president that for such a large project, the company would have to use outsourced employees. Past experience indicated a fifty-fifty chance of a strike. Technical Details of the stadium: The stadium is an indoor structure with a seating capacity of 20,000. The project begins with clearing the site, an activity that lasts eight weeks. Once the site is clear, the work can start simultaneously on the structure and on the field. The work in the field involves surface drainage which lasts eight weeks, followed by filling for the playing field and track. Only with the completion of the filling (14 weeks) can the installation of the artificial......

Words: 363 - Pages: 2

Premium Essay

Sharon Construction Company

... Abstract This paper will discuss a case study from the text book “Project Management: A Managerial Approach.” The case is titled “The Sharon Construction Corporation.” The case consists of a construction company that has won a contract for an upcoming project. The project is erecting a 20,000-seat stadium. The case is very in-depth in regards to the different stages of the project, and the amount of time that each stage will take to complete. Within the case, there are five different proposals that are given by the management team. Each of these proposals contains ways to reduce time, and work around specific identified risks that are associated with completing the project. In this paper, I will discuss the overall project timeline, the five proposals, and identify the best solution to complete the project on time, and with the most profit possible for the company. Project Overview The upcoming project for The Sharon Construction Corporation is a project that has the potential to generate a substantial profit of $300,000. In order to maximize this potential profit, there are several risks that are associated that need to be analyzed and thought out to arrive at the most economically efficient conclusion. The first risk is the complication of the dates associated with the start and completion date. Construction on the project must start by February 15. Once the project is started, the company has one year to complete. A penalty clause of $15,000 per......

Words: 2854 - Pages: 12

Free Essay

Macbeth

...Shakespeare in Film Individual Assignment Macbeth is well known to be one of Shakespeare’s shortest yet darkest tragedies. The rich, psychological turmoil experienced by the main characters and the incorporation of elements such as the supernatural culminates in a tragedy that is one of Shakespeare’s most intense and grim. I will be examining the 1971 Roman Polanski film due to the unique life story of the director and the gruesome murders that occurred prior to the film. The film employs the use of gratuitous violence, nudity and graphic imagery that far exceeds that of the text, which Roman Polanski masterfully uses to highlight the inherent madness and evil that drives Macbeth and in doing so, successfully creates an psychologically disturbing film with an atmosphere of perpetual dread. Firstly, one distinct feature about the film that differs from the text is the inclusion of nudity seen in several scenes. Macbeth itself draws largely upon the theme of the occult and madness as the main driving forces, with the inclusion of the prophetic apparitions, visions of ghosts and mental breakdowns. The scene showing Macbeth seeks out the witches for the 2nd time exemplifies the occult brilliantly as it opens to a huge coven of naked witches huddled around the cauldron whilst chanting “Double, double, toil and trouble; Fire burn, cauldron bubble”. In the book, there was no mention of other witches apart from the three and by including the scene, the huge gathering...

Words: 1232 - Pages: 5

Free Essay

Crminol; Kn

...Born in Ohio in 1934, Charles Manson is notoriously connected to the brutal slayings of actress Sharon Tate and other Hollywood residents, but he was never actually found guilty of committing the murders himself. However, the famous Tate-La Bianca killings have immortalized him as a living embodiment of evil. Images of his staring "mad eyes" are still used today to illustrate countless serial-murder news stories. The Manson Family—including Charles Manson and his young, loyal dropout disciples of murder—is thought to have carried out some 35 killings. Most were never tried, either for lack of evidence or because the perpetrators were already sentenced to life for the Tate/La Bianca killings. In 2012, Manson was denied parole for the 12th time. Charles Manson I believe was not crazy but very clever individual. Manson had a group of people he referred to as his “family” he was a very manipulative man to the people around him. His followers numbering round the one-hundreds, also including a small portion of impressionable young girls. He had them all to believe without question that he was Jesus and his prophecies of a race war. Manson was not only influenced by drugs such as LSD but by art works and music of the time such as The Beatles song “Helter Skelter” from their white album. The first murders took place on August 9, 1969, at Roman Polanski’s Beverley Hills home at 10050 Cielo Drive. Manson chose his four most best comrades- Charles “Tex” Watson, Susan Atkins,......

Words: 1308 - Pages: 6

Free Essay

Working on It

...Sharon: Please read my feedback and revise your Topic Proposal Form accordingly. Title it as Topic Proposal Rev 1. Post as soon as possible in the Week One Dropbox and let me know when you post it. I hope this feedback is helpful. Dr. Gurley Topic Proposal Form Date 09/03/14 Your Name Sharon Story Plan (1 or 2) Plan 1 Name of Your Organization and Contact Person if Plan 1 is chosen (if confidential you may email this info to me) Riverside Casino and Golf Resort / Stacy Benson Topic Title Performance Reviews NO. This title won’t work. What about performance reviews? If you were doing a simple research paper you could write about performance reviews based on research alone. In this Sr Paper you must determine the state of the art based on your Literature Review. Then you will give the background of the problem and discuss it. This must all lead to two Courses of Action (COAs; solutions) that are tied to your title and problem. You need a “product” such as a process, a plan, a strategy, a program – something that can be recommended and implemented. Problem Statement (if not finalized post a draft – focus on the "pain.") The problem is that after initial training employees are not being reviewed for current performance. Suggest that after this initial statement you add something more about the problem. Brief Topic Overview The casino is experiencing a high turnover rate of employees because after their initial training they are put on the floor......

Words: 640 - Pages: 3

Free Essay

Test

...of grand theft.                                                                   Holley added, however, than whatever the value of the jewelry she still intends to show “Ms. Lohan didn't steal anything." Though the one-time Disney starlet claimed she was loaned the necklace, jeweler Geoff Kaman and his wife reported it stolen after pictures surfaced of Lohan wearing it. Upon hearing she was under investigation, LiLo turned the necklace over to cops. "i would never steal, in case people are wondering. I was not raised to lie, cheat, or steal," she wrote on her new Facebook page Thursday. Lohan was released on $40,000 bail on Wednesday after appearing in court wearing a skin-tight, white Kimbley Ovitz mini dress that was compared to Sharon Stone's infamous "Basic Instinct" frock. "what i wear to court shouldnt be front page news. it's just absurd," Lohan wrote on Facebook the next day. But the clothing quickly sparked a mad-dash by women looking to slip into the stylish attire, which was soon sold out in online...

Words: 365 - Pages: 2

Premium Essay

A Peaceful Evacuation

...In December 2003, Israeli Prime Minister Ariel Sharon shocked the world when he announce that Israel will disengage from the Palestinians, a Disengagement Plan, primarily from the Gaza Strip. There were several protests that erupted due to this news, as well as a human chain that was created in protest to stop the disengagement. Once it was decided that the Israeli Defense Forces (IDF) would carry out the evacuation mission, the issue of how this move would occur arose. Major General Dan Harel, head of the Southern Command was in charge of the entire mission. Harel decided to have a roundtable that would decide how this mission was to be executed. Among those that were invited was Lieutenant Colonel Daniel, a chief psychologist of the Southern Command. Daniels leadership proved to be that of someone that is consultative. A consulting leader is one that is concerned about the support dimension, but there is still a high emphasis on the task itself (Kloppenborg, 96). This is demonstrated when Daniel was first given the position and the task. Daniel main focus was first the well-being of that of the people. He gathered the other IDK psychologists, listened to them and their problems, and they all identified how they were going to complete the mission. The importance of listening to the other phycologists was to determine the mental capacity of the evacuators. Daniel also did research on other large evacuations to see what measures were taken during those instances. His research...

Words: 1133 - Pages: 5

Premium Essay

Strategic Plan

...BUS/475 Integrated Business Topics December 15, 2011 Strategic Plan - Part I: Conceptualizing a Business Land Forms Construction is a general engineering and landscape contractor located in Laguna Niguel, California. The company has been in business for over 21 years. The owners Jeff and Anna Tracy started out as a landscape contractor concentrating mainly on commercial projects in Southern California. The company expanded its services into Northern California and Arizona. In 2010, Jeff Tracy also added value to his company by acquiring a General Engineering license to add value to the services offered at Land Forms. Mission Statement Land Forms Constructions' mission is to provide the finest quality results in all that we do. It is our goal to undertake all projects with the attitude of 100% performance in all respects, including: 1. Safety of both the public and our employees and customers. 2. Compliance with environmental laws and regulations. 3. Quality of products and services. 4. Customer relations. It is our view that no project is successful unless our client is satisfied, the project was completed both on time and within budget, and the job has been built using the finest materials and methods so as to provide the maximum value to our customer. Sunburst Landscaping plants a landscape architect’s vision making a construction project come alive. For 34 years we have followed our mission statement of providing quality service to......

Words: 330 - Pages: 2

Free Essay

It Integration

...In order to successfully implement a new IT system, there are certain questions that the company has to ask before making a decision on whether or not to commence renovation. The array of question does not only include such issues as whether it is worthwhile for a company to invest its resources (staff and finance), the short-term and long-term benefits of the new IT system, better reach for the customers, lesser uncertainty etc. but also the risks that the company opens itself to with the introduction of new systems and the ways to eliminate most of it so as to ensure that the introduction of the new IT system does not go over the budget. The biggest issues I can identify are as follows: * Compliance with the overall business strategy * Compatibility with the existing systems * Staff expertise and their attitude to the proposed changes * Staff training * Day-to-day controls, function controls, etc. The main idea behind implementing a major new IT system is to facilitate better communication of information amongst all the parties involved in the value chain, including the customers. The more relevant data is collected and analyzed the more efficient and responsive the value chain is. The question is what information to regard relevant and useful and the other way round. In my understanding, the main thing is to remember that optimization should not be limited to a certain function and/or department but on the contrary, it should be inclusive of all......

Words: 599 - Pages: 3

Premium Essay

Project Delivery at Autodesk, Inc.

...Table of Contents Executive Summary 3 Determine how you would manage the morale of the team related to the change management 4 Critique what steps must be taken to ensure that all team members learn of changes 5 Assess the timing of communication as critical to the success of the project 6 Assume that two (2) key members of the were replaced during the executing phase of the project due to family crisis situations. Explain the actions you would take to establish trust and credibility with the remaining project participants involved in the situation 7 References 10 EXECUTIVE SUMMARY Design technology company Autodesk recently expanded its presence in New England with a new headquarters for its Architecture, Engineering, and Construction (AEC) Solutions Division. It is located in Waltham, Massachusetts and the new facility accommodates staff expansions and offers additional space for meeting with its customers, the press, and the community. Autodesk viewed the project as an opportunity to implement several new trends in the building industry, including integrated project delivery (IPD), sustainable design, digital design-to-fabrication, and the technical process underpinning all of them—building information modeling (BIM). According to Phil Bernstein, FAIA, vice president, Industry Strategy and Relations of the AEC Solutions Division at Autodesk, felt strongly that it was important to use these methodologies because they advocated their use to millions of......

Words: 2317 - Pages: 10

Premium Essay

Integrated Project Delivery at Autodesk, Inc.

...Integrated Project Delivery at Autodesk, Inc. BUS 518: Project Management Leadership Strayer University, Washington DC December 1, 2011 Abstract Integrated Project Delivery (IPD) is a collaborative alliance of people, systems, business structures and practices that harness the talents and insights of all participants to optimize project results, increase value to the customer, reduce waste, and maximize efficiency through all phases of design, fabrication, and construction. Autodesk, Inc. used this approach when they built their LEED Platinum certified, award winning headquarters. The IPD approach was highly effective on this project, but it was not without its problems, especially with regard to changes in the project’s scope. The overall success of the project was due to several factors, including a clear vision for the project, identifying three types of scope changes in advance, and identifying what does not work. These topics will be explored in this paper. As project leader for the office building construction project, formulate a vision statement for the team project. Gray and Larson (2009) point out that the vision of a project is less tangible than the project scope. The vision is the image the team members hold in common about the project, such as, how will the project look when it is complete, how the team members will work together and/or how will the customers accept the project. They state that in its simplest terms, a shared vision answers......

Words: 2300 - Pages: 10

Premium Essay

Project Managment

...* Procure Building Site, Permits, and Appropriate Approvals * Construct the Huntsville Plant Building * Landscaping on Site * Personnel Recruiting for Plant Operations * Procure Equipment, Raw Material and Truck Fleet * Install Equipment * Create Product Distribution Plan and Pre-Production Plan * Start Up Production and Distribution Out of Scope * Geothermal Heating * Solar Powered Electric Feed * Multi-Level Parking Garage * In-House Food Court * Construction of Separate Distribution Facility | Objectives | | The objective is to construct a new plant in Huntsville Alabama between April 18, 2011 through June 30, 2012. This project is one of several initiatives that align with achieving the SEITZ Corporation’s strategic goal of doubling total sales within the next decade. The construction and project should not exceed $2,750,000. | Assumptions | Construction of the Huntsville plant should follow similar construction by the SEITZ Corporation. | | Constraints | Noticeable constraints are within the project team and their individual expertise. Additional team members will be needed to cover a wider variety of knowledge and...

Words: 513 - Pages: 3

Premium Essay

Huntsville Project Scope

...January 2010, the board of directors of SEITZ Corporation decided to select an investment project that would best achieve the strategic goals in the next fiscal year. The project that was selected is the construction of a new plant in Huntsville, Alabama. Walter Seitz is the Project Sponsor. $2,750,000 has been budgeted for this effort, and it should begin by April 18, 2011 and should be fully operating by June 30, 2012. Project Product This section is typically an amplification of the product description from the Project Charter. Project Deliverables 1) Select resources such as: Architect, Real Estate Consultant, and General Contractor. 2) Recruit and Train Managers for Huntsville Plant. 3) Create a Pre-Production and Production Plan. 4) Create a Building Concept and Design. 5) Procure Building Site, Permits, and Appropriate Approvals. 6) Construct the Huntsville Plant Building. 7) Landscaping on Site. 8) Personnel Recruiting for Plant Operations. 9) Procure Equipment, Raw Material and Truck Fleet 10) Install Equipment. 11) Create Product Distribution Plan and Pre-Production Plan. 12) Start Up Production and Distribution Project Objectives To expand Seitz Corporation in accordance with the Company’s Strategic plan set by the Board of Directors by construction of a new plant in Huntsville, Alabama, within a budget of $2,750,000, which is to be operational by June 30, 2012.The aforementioned strategic plan is listed below in order of priority.1.......

Words: 303 - Pages: 2

Premium Essay

Rahul

...The term ‘real estate’ is defined as land, including the air above it and the ground below it, and any building or structures or structures on it. It is also referred to as realty. It covers residential housing, commercial offices, trading spaces such as theaters, hotels and restaurants, retail outlets, industrial building such as factories and government buildings. Real estate involves the purchase, sale and development of land, residential and non – residential buildings. The main players in the real estate market are the landlords, developers, real estate agents, tenants, buyers etc. The activities of the real estate sector encompass the housing and construction sectors also. The real estate sector in India has assumed growing importance with the liberalization of the economy. The consequent increase in business opportunities and migration of the labour force has, in turn, increased the demand for commercial and housing space, especially in residential segment. The real estate sector has emerged as one India’s largest drivers of economic growth. The real estate boom in India was inextricably linked to the country’s economic stability, which had made India a preferred investment destination. India is on the verge of becoming one of the fast-growing economies, driven by many factors including multinational entrepreneurialism, local stock markets, robust economy-changing demographics and the overall emergence of India on the global stage. With great demand for housing...

Words: 428 - Pages: 2